Sub topic 7
Why Batches and Work in Progress Slow Flow
Prerequisites
Assume you understand the basic idea of a process: work enters, passes through steps, and becomes an output for a customer. You should also be comfortable with simple rates and averages. In this chapter, flow means work moving through a process steadily, with little waiting between steps.
Two common obstacles to flow are large batches and excess work in progress (WIP). WIP is work that has started but is not finished. Examples include partly assembled products, unanswered support tickets, and software features waiting for review.
How batches create waiting
A batch is a group of items processed together before the next step receives them. Batching can seem efficient because it reduces setup work. For example, a machine may be configured once to produce 100 parts instead of being configured 100 times.
The problem is that downstream work often cannot begin until enough of the batch is ready. The first item may finish early, but it waits while the remaining items are completed. The batch therefore increases the time before value reaches the customer.
Suppose a process has two steps:
- Step A completes one item per hour.
- Step B can begin only after receiving a batch of 10 items.
Step B starts after 10 hours. The first item waits almost 9 hours, while the last item waits almost none. The average waiting time before Step B is about 4.5 hours. If Step B could receive items one at a time, it could start after the first hour.
Small batches reduce this waiting. They also expose problems sooner. If one item has a defect, a small batch limits the number of affected items and prevents the defect from moving far through the process.
def average_batch_wait(batch_size, hours_per_item):
"""Average wait for an item before the next step starts."""
return (batch_size - 1) * hours_per_item / 2
for batch_size in (1, 5, 10):
wait = average_batch_wait(batch_size, 1)
print(f"Batch of {batch_size}: average wait = {wait:.1f} hours")A smaller batch is not always better. Frequent setups, transport costs, or strict quality requirements may justify some batching. The useful question is whether the reduced setup effort is worth the extra waiting, defects, and coordination.
How excess WIP creates queues
When each step starts work whenever it can, unfinished items accumulate between steps. These items form queues. A queue can make a process look busy, but it usually increases the time before completion.
High WIP causes several problems:
- People spend time searching, sorting, and prioritizing items.
- Work is interrupted when an urgent item arrives.
- Defects remain hidden inside unfinished work.
- Items become outdated while they wait.
- Teams begin many tasks but finish few of them.
Multitasking makes this worse. Switching between tasks adds setup time for people, just as changing machine settings adds setup time for equipment. A team with five partially completed tasks may feel productive, but the customer receives nothing until one task is finished.
Little’s Law expresses the relationship:
average cycle time = average WIP / average throughput
If a team completes 5 items per day, 30 items in progress imply an average cycle time of 6 days. Reducing WIP to 10 items, while keeping throughput at 5 items per day, reduces the average cycle time to 2 days.
Choosing a practical batch size
Start by asking where waiting occurs rather than assuming every step should use one-piece flow. Compare these factors:
- Setup time for changing between items
- Waiting time caused by the batch
- Cost of moving or storing unfinished items
- Risk that defects affect the whole batch
- Demand variability and customer urgency
A useful improvement is to reduce the batch gradually. Measure lead time, defects, setup effort, and throughput after each change. The goal is not the smallest possible batch. The goal is a batch size that supports steady flow without creating unreasonable setup costs.
Exercise
A team completes 4 requests per day and has an average of 20 requests in progress. What is the average cycle time, and what would it become if WIP fell to 8 requests with the same throughput?
Show answer
Using average cycle time = WIP / throughput, the current cycle time is 20 / 4 = 5 days. With 8 requests, it becomes 8 / 4 = 2 days.