Sub topic 10
Kanban and WIP Limits as a Pull Mechanism
This chapter assumes you understand basic process steps, value streams, and the difference between throughput and cycle time. You should also be comfortable with simple ratios. Kanban is a practical way to apply Lean’s pull principle: work starts because the next step is ready for it, not merely because someone wants to keep the upstream step busy.
What “pull” means
A pull system lets downstream demand control upstream work. A new item enters a step only when that step has available capacity and a real need for more work.
In a push system, each step sends work forward as soon as it finishes. This can create queues. The next step receives more work than it can process, so unfinished items accumulate.
In a pull system, the downstream step requests or “pulls” the next item. This keeps work in progress, or WIP, within a deliberate limit.
WIP is work that has started but is not yet finished. Examples include:
- Orders waiting for assembly
- Claims waiting for review
- Features being coded but not released
- Parts waiting between machines
Reducing WIP usually exposes problems more quickly. A blocked item cannot hide in a large queue, and teams can focus on finishing existing work.
Kanban as a visible pull system
Kanban is a method for managing the flow of work with visible signals. A simple board might contain these columns:
| Ready | In progress | Review | Done |
|---|---|---|---|
| Items waiting to start | Items currently being worked on | Items awaiting verification | Accepted items |
Cards represent work items. Moving a card shows its current state. Each active column can have a WIP limit. For example, the Review column might allow no more than two cards.
When Review reaches its limit, the upstream team should not start another item. Instead, it helps complete or clear the review queue. This is the key behavior: the full downstream step stops upstream production.
flowchart TD
A[Ready queue] -->|Free capacity in progress| B[In progress]
B --> C[Review]
C --> D[Done]
C -. WIP limit reached .-> E[Upstream helps clear review]
E --> CChoosing and using WIP limits
A WIP limit should reflect the capacity and coordination needs of a step. A limit that is too high allows queues to grow. A limit that is too low may leave people idle when work requires long setup or specialized skills.
Start with a limit close to the number of people or processing units in the step, then adjust it using evidence. Watch for:
- Items waiting because the next step is full
- People starting new work instead of helping finish current work
- Frequent blocked items
- Long cycle times despite steady output
- Quality problems caused by rushing to clear a queue
The goal is not to maximize local utilization. The goal is to improve the whole system’s delivery of valuable work.
WIP, throughput, and cycle time
Little’s Law connects these measures:
\[ \text{Average WIP} = \text{Throughput} \times \text{Average cycle time} \]
Rearranged:
\[ \text{Average cycle time} = \frac{\text{Average WIP}}{\text{Throughput}} \]
If a team completes five items per day, 30 items in progress imply an average cycle time of six days. If the team limits WIP to 10 while maintaining the same throughput, average cycle time falls to two days.
def avg_cycle_time(wip, throughput_per_day):
"""Little's Law: average cycle time = WIP / throughput."""
return wip / throughput_per_day
print(avg_cycle_time(30, 5)) # 6.0 days
print(avg_cycle_time(10, 5)) # 2.0 daysThe calculation describes an average, not a promise for every item. Variation, rework, and blocked work can make individual results different.
Common errors
A board alone does not create pull. Common mistakes include:
- Setting WIP limits but ignoring them
- Counting partially started work as “almost done”
- Adding an expedite lane that bypasses every limit
- Measuring only individual busyness
- Lowering limits without resolving skill or equipment constraints
- Treating blocked work as completed
A useful response to a full column is to swarm: several people help finish, test, or unblock the oldest item. This improves flow without creating more WIP.
Exercise
A process completes four claims per day and has an average WIP of 20 claims. What is its average cycle time? What would happen if WIP fell to 12 while throughput stayed constant?
Show answer
The current average cycle time is 20 / 4 = 5 days. At 12 claims of WIP, the average cycle time would be 12 / 4 = 3 days.