Sub topic 8
Surfacing Risks, Assumptions, and Dependencies
Who this chapter is for
This chapter assumes you can already describe a project's goals and scope, and that you have a draft timeline with milestones. It builds on those. The agenda slot is "Risks and open questions" (about seven minutes in the sample 60-minute kickoff), so the chapter also covers how to use that slot well and how to hand unresolved items to a longer process afterward.
The aim of this part of the kickoff is not to produce a complete risk register. The aim is to get the team's early concerns, hidden beliefs, and outside needs onto one page, each with a named owner, before work starts.
Three different things
People often mix these three terms. Separating them makes the discussion faster, because each type needs a different response.
| Item | What it is | Example | Typical response |
|---|---|---|---|
| Risk | An uncertain event that could hurt (or help) the project if it happens | The vendor may deliver the API late | Assess, then avoid, reduce, transfer, or accept |
| Assumption | Something the plan treats as true without having confirmed it | The test environment will be ready by week 2 | Validate it, or record it and watch it |
| Dependency | Something the project needs from outside the team, or that must happen in a set order | Legal must approve the contract text before launch | Name the provider, agree a date, track it |
A risk is a possibility. An issue is a risk that has already happened, and it needs action now rather than assessment. If someone says "the budget has been cut," that is an issue, not a risk. Treat it as a decision or action item.
An assumption that turns out false usually becomes a risk or an issue. For this reason, assumptions are often the most productive thing to probe in a kickoff. Many are never said aloud because everyone believes them.
Why raise them at the kickoff
At kickoff, most of the plan is still cheap to change. Moving a milestone, adding a person, or asking another team for a commitment costs little now and more later.
The meeting also puts people from different functions in one room. Each sees a different part of the project, so the combined list is better than any one person's list. An engineer may know about a fragile system. A finance partner may know about a budget freeze. The sponsor may know about a competing priority. None of them may realize the others do not know.
There is a social benefit too. If the facilitator asks for concerns early and treats them as useful, people are more likely to speak up later.
Preparing the material
Do not start with a blank page. In pre-kickoff preparation, draft a short list from sources you already have:
- The project brief or statement of work. Look for phrases such as "subject to," "assuming," or "pending."
- Lessons learned from similar past projects.
- Conversations with the sponsor and key leads before the meeting.
- The draft timeline. Look for tasks with no slack, tasks that wait on another team, and milestones that depend on a single person.
Bring this list as a starting point, labeled "draft for discussion." A seeded list gets the conversation going and shows what a useful contribution looks like. Do not present it as complete. If you do, people will assume the thinking is done and stay quiet.
Also decide in advance which items you will not discuss at length. If a risk needs a specialist and a long analysis, plan to take it offline with an owner and a date.
Running the segment
Use a short, repeatable sequence. With about seven minutes, a structure keeps you from spending all of them on the first topic.
- Frame it (1 minute). Explain the three categories. Say that raising a concern is a contribution and not a criticism of the plan.
- Collect (3 minutes). Ask open questions and write each item where everyone can see it. Do not debate yet.
- Sort and pick (2 minutes). Group duplicates. Choose the few items that look most serious, using a quick show of hands or the sponsor's judgment.
- Assign (1 minute). Give each chosen item an owner and a date for the next step.
Questions that work
Closed questions such as "Any risks?" often get silence. Try prompts that make it easy to answer:
- "Imagine it is the delivery date and we are late. What happened?"
- "What are we counting on that we have not yet confirmed?"
- "Which parts of this plan depend on a team that is not in the room?"
- "What has gone wrong on a project like this before?"
- "Who here is worried about something and has not said it yet?"
The first prompt is sometimes called a premortem. It works because imagining a failure lets people name causes without sounding negative about the plan.
Collect before you evaluate
Separate gathering from judging. If you discuss each item as it arrives, early items eat the time and the quieter people never get a turn. Two practical options:
- Ask everyone to write items on sticky notes or in a shared document for two minutes in silence, then read them out.
- In a remote meeting, use the chat or a shared board so people can add items at the same time.
Rating and responding
You do not need a detailed scoring model in the meeting. A simple three-level scale for likelihood and impact (low, medium, high) is enough to decide which items deserve attention. Items rated high on both go to the top.
For each risk you choose to act on, pick a response:
| Response | Meaning | Example |
|---|---|---|
| Avoid | Change the plan so the risk cannot occur | Use a proven library instead of a new one |
| Reduce | Lower the likelihood or the impact | Start the vendor integration early to expose problems |
| Transfer | Shift the consequence to another party | Buy insurance or add a contract penalty |
| Accept | Do nothing now, and agree to live with it | Minor schedule slip on a non-critical task |
Accepting a risk is a legitimate decision, but it should be a decision made by someone with authority and written down. An unrecorded "we'll deal with it" is not acceptance, it is avoidance of the topic.
Recording the items
Write each item in a form that can be acted on. A vague entry is hard to own and impossible to close.
- Weak: "Vendor risk."
- Better: "The vendor may deliver the payment API after 15 June, which would delay integration testing. Owner: Priya. Next step: ask the vendor for a written delivery date by Friday."
A good risk statement has a cause, an event, and an effect. A good assumption statement can be checked: someone can confirm it or disprove it. A good dependency entry names the provider, the thing needed, and the date it is needed.
A minimal log can be a table, and it can live in the same document as your notes:
### Risks, assumptions, dependencies
| ID | Type | Statement | Rating | Response / next step | Owner | Date |
|----|------|-----------|--------|----------------------|-------|------|
| R1 | Risk | Vendor may deliver the payment API after 15 June, delaying integration testing | High | Reduce: request written delivery date | Priya | Fri |
| A1 | Assumption | Test environment is ready by week 2 | Medium | Validate with infrastructure team | Sam | Next Tue |
| D1 | Dependency | Legal approval of contract text needed before 1 Aug | High | Agree review slot with Legal | Dana | Next Mon |Keep the IDs. They let the follow-up email and later status reports refer to the same item without retyping it.
Common errors
- Treating the segment as a formality. If it is the last item and time has run out, you will skip it. Protect the slot, or move it earlier than the communication plan.
- Letting the sponsor speak first. Senior people can unintentionally close off dissent. Collect written items first, or ask the sponsor to speak last.
- Solving every item in the room. This burns time and leaves most of the attendees idle. Assign an owner and move on.
- Items with no owner. A shared concern is owned by nobody. Every row needs one named person.
- Confusing issues with risks. Current problems need decisions now, so put them in the action list.
- Never revisiting the list. A log written once and filed is decoration. Add a standing review to your regular status meeting.
- Ignoring positive risks. Opportunities, such as a chance to reuse another team's tool, can also be raised and owned.
Dependencies and the timeline
Dependencies connect directly to the timeline you just walked through. For each milestone, ask what it needs and from whom. Then check the provider's dates against yours.
Look especially for:
- External dependencies on other teams, vendors, or approvals. You do not control their schedules, so you need their agreement.
- Sequential dependencies, where one task cannot start until another finishes.
- Shared-resource dependencies, where the same person or environment is promised to several projects.
If an important provider is not at the kickoff, record the dependency and assign someone on your team to contact them. Do not assume silence means agreement.
Carrying the list forward
After the meeting, the log joins the notes and the follow-up message. The email should list high-priority items and the owners' next steps, and mention the ones still open. Then schedule the first review, for example at the first weekly status meeting, so the items get checked while memories are fresh.
For a small project, a six-line list may be all you need. For a large or regulated project, the kickoff list feeds a formal risk register with scoring and reporting. The kickoff's job is the same in both cases: surface the items early and give each one an owner.
Exercise
During a kickoff, an engineer says, "We're assuming the data warehouse team will give us read access by week 3." Classify this item, and rewrite it as a log entry that someone can act on. Include a type, a statement, a next step, an owner role, and a date.
Show answer
It is both an assumption (access is believed but not confirmed) and a dependency (it needs a decision by another team). Log it as a dependency with the assumption noted. Example entry: "D2 | Dependency | Data warehouse team grants the project read access by the end of week 3; not yet confirmed | Next step: send an access request and ask for a written date | Owner: engineering lead | Date: end of this week." The key points are that it names the provider, states what is needed and by when, and has a next step with an owner and a date.
Exercise
You have seven minutes for risks. The sponsor starts describing a single large risk and has spoken for four minutes. What two things can you do to protect the segment, and what should you do with the risk itself?
Show answer
Thank the sponsor, then move the group on by pausing the discussion and returning to the collect step, so others can add items (for example, by asking everyone to write items for two minutes). Then sort and assign. Take the large risk offline: record it with an owner and a date for a separate working session, so it gets proper analysis without using the whole segment.