Preparing before the meeting
A kickoff succeeds or fails mostly before anyone joins the call. The meeting is a poor place to discover that the sponsor and the delivery lead disagree about the launch date. It is also a poor place to read a 20-page brief for the first time. Preparation moves those discoveries earlier, when they are cheap to fix.
This chapter assumes you know what a kickoff is for and who should attend, as covered in the earlier chapters. It also assumes you can get hold of whatever project brief, charter, or statement of work exists. The next chapter turns the preparation described here into a time-boxed agenda.
What preparation produces
Preparation has four outputs:
- A single source of truth for the project's goals, scope, and constraints, usually a one- or two-page brief.
- A draft of the things the meeting will confirm: timeline, roles, and risks.
- A list of open questions, split into those you can resolve before the meeting and those that need the group.
- A pre-read that attendees receive in advance, with a clear request for what they should do with it.
The draft is the key idea. People react to a concrete proposal far better than they contribute to a blank page. A kickoff built on drafts is a confirmation meeting with some discussion. One built on blank pages turns into planning, which takes much longer than the hour you booked.
Gather and reconcile the inputs
Start by collecting every document that describes the project. Typical sources are the business case, the charter, a contract or statement of work, earlier emails, and notes from sales or discovery conversations.
Then read them against each other. The most common source of trouble is not missing information but conflicting information. A contract may promise a feature that the charter marks as out of scope. A sponsor's email may give a different date from the plan.
Keep a short list of conflicts as you read. For each one, write down:
- what the two sources say,
- who can settle it,
- whether it must be settled before the meeting or can be settled in it.
Settle conflicts about facts before the meeting. Bring conflicts about priorities or trade-offs to the meeting only when the right people will be there to decide.
Write the one-page brief
The brief is your own working summary, and it becomes the core of the pre-read. Keep it to one page so people actually read it. A workable structure:
| Section | What to write | Common error |
|---|---|---|
| Purpose | Why the project exists, in two or three sentences | Describing the solution instead of the problem |
| Goals and success criteria | Measurable outcomes and how they will be judged | Vague goals such as "improve the experience" |
| Scope | What is in, what is out, and the main deliverables | Leaving "out" empty |
| Constraints | Fixed dates, budget, technology, compliance | Mixing constraints with wishes |
| Known stakeholders | Names and roles | Listing teams instead of people |
If you cannot fill a section, that gap is useful information. Move it to the open questions list.
Draft what the meeting will confirm
Prepare first drafts of the timeline, the roles, and the risks. They can be rough, but they must exist.
- Timeline: list the fixed dates, a sensible set of milestones, and the dependencies you already know about. Mark each milestone as "fixed" or "estimated" so no one treats a guess as a promise.
- Roles: list each area of work and a proposed owner. Where you do not know the owner, write "to be assigned" rather than leaving it out.
- Risks: list the five or so you would worry about most, each with a proposed owner. Ask two or three experienced people what could go wrong and add their answers.
Mark every draft clearly with a "Draft, to be confirmed" label. This tells attendees that you want corrections, and it shows you have done the groundwork.
Pre-wire the people who matter most
Pre-wiring means talking one-to-one with key people before the group meeting. It is the step intermediate project managers most often skip, and it prevents most of the awkward moments in a kickoff.
Talk with these people in advance:
- The sponsor. Confirm that the stated goals, success criteria, and constraints are what they believe. Agree what they will say in their opening section, and ask them to keep it short and clear.
- Owners of large areas of work. Check that they accept the role you plan to assign them and that their estimates are realistic.
- Anyone likely to object. Find out about concerns now. A concern raised privately can often be addressed before the meeting. The same concern raised publicly can derail it.
The aim is not to decide everything in private. It is that nobody in the meeting is surprised by something that affects them directly. If a person learns about their role for the first time in the kickoff, preparation has failed.
Split the open questions
Collect every unresolved item and sort it into one of three groups:
- Answer now. Facts someone can look up or confirm before the meeting, such as who has access to a test environment.
- Decide in the meeting. Questions that need several people present, such as how to sequence two competing deliverables.
- Park. Questions that do not affect the first phase of work. Record them with an owner and a review date so they are not lost.
Answering the first group before the meeting buys you time for the second. If you arrive with ten open questions and no sorting, the meeting spends its time on the easiest ones.
Write a pre-read that people will read
A pre-read is the material sent before the meeting. Most pre-reads fail because they are too long and because they do not say what the recipient should do.
Keep these rules:
- Send it two to three working days ahead. Earlier is forgotten, and later is ignored.
- Put the ask in the first two lines: what to read, how long it takes, and what to bring.
- Attach the one-page brief, the draft timeline, and the draft roles. Link longer documents instead of attaching them.
- Ask each person for one specific thing, such as "confirm your area's owner" or "bring your top risk".
Here is a template you can adapt:
Subject: <Project name> kickoff on <date>: 10-minute pre-read
Hi all,
Our kickoff is on <date> at <time>. Please spend about 10 minutes
before then reading the attached one-page brief and draft timeline.
**What I need from you before the meeting**
- <Name>: confirm you can own <area of work>
- Everyone: send me your single biggest concern by <date>
**What we will decide in the meeting**
- Scope boundaries and who approves changes
- Milestone dates and owners
Draft documents are marked "Draft, to be confirmed". Corrections
are welcome.Collecting concerns by email also gives quieter attendees a way to be heard, which you can use during the meeting.
Handle logistics
Logistics are dull but they cause real failures. Check each item below no later than the day before.
- Invitation: it includes the purpose, the agenda or a link to it, and the pre-read.
- Room and equipment: you have tested the screen, audio, and video setup. For remote attendees, confirm that the link works and that recording or captions are available if needed.
- Roles for the meeting: a facilitator and a note-taker are named. If you are both, plan for it, because doing both well is hard.
- Materials: the slides, the notes template, and the shared action-item list are open and ready.
- Time zones and access: you have checked every attendee's local time and confirmed that everyone can open the shared documents.
Run a readiness check
On the day before, ask yourself five questions:
- Has the sponsor confirmed the goals and what they will say?
- Do the key owners know their proposed roles?
- Do I have drafts of the timeline, roles, and risks?
- Did people receive the pre-read, and have I had replies from the key ones?
- Do I know which questions must be decided in the room?
If you answer "no" to any of these, fix it or decide how to handle it. If the sponsor has not confirmed the goals, for example, consider a short call or a delay. Holding a kickoff that you know is unprepared costs more than moving it by a few days.
Common errors
- Preparing too late. Starting the day before leaves no time to reconcile conflicts or pre-wire anyone.
- Over-preparing the content. A 40-slide deck signals that the meeting is a presentation. Aim for a short brief and room for discussion.
- Treating drafts as final. If you present the timeline as settled, attendees will not challenge it, and problems will surface weeks later.
- Sending the pre-read with no ask. Without a request, most people skip it.
- Ignoring silence. If key people do not respond to the pre-read, follow up directly instead of assuming agreement.
Exercise
Two days before the kickoff, you notice that the contract lists a reporting dashboard as a deliverable, but the project charter lists it as out of scope. The sponsor and the client lead will both attend. What do you do before the meeting, and what do you leave for the meeting?
Show answer
Treat it as a conflict about facts and priorities and handle it in three steps. First, record the conflict in your list: what each source says, and who can settle it (likely the sponsor, possibly with the client lead). Second, pre-wire the sponsor privately to find out which document reflects their intent, and to learn whether the client expects the dashboard. Third, decide how to present it. If the sponsor confirms the dashboard is out of scope, state that in the draft scope and explain it in the meeting. If the answer is unclear or involves a trade-off with the client, list it under "Decide in the meeting" and make sure both people are prepared for it, rather than letting it surface as a surprise. Either way, mark the scope section "Draft, to be confirmed".
Exercise
Your pre-read email is three pages long, was sent the morning of the kickoff, and asks everyone to "review the attached". Name three problems and fix each one.
Show answer
(1) It is too long: cut it to a one-page brief plus a draft timeline and draft roles, and link longer documents. (2) It was sent too late: send it two to three working days before the meeting. (3) The ask is vague: state in the first two lines what to read, how long it takes (for example 10 minutes), and one specific request per person, such as confirming an owner or sending their biggest concern by a set date.