Sub topic 10
Setting Working Agreements
Working agreements are short, explicit statements of how the team will behave while it works together. They cover things like response times, meeting etiquette, how decisions get made, and what to do when someone disagrees. This chapter shows you how to draft them during a kickoff, how to keep them useful, and how to avoid the common ways they fail.
Prerequisites
This chapter assumes you have read the earlier chapters on roles and responsibilities and on the communication plan. You should know who owns which area and which channels the team will use. Working agreements build on both. The communication plan says where and how often the team talks. Working agreements say how the team behaves when it does.
What a working agreement is, and what it is not
A working agreement is a small set of rules the team writes for itself. Three features define it:
- Team-authored. The people who must follow it help write it.
- Observable. Anyone can tell whether a rule was followed.
- Revisable. The team can change it when it stops working.
It is not a corporate policy, a code of conduct, or a contract. Company policies already exist and take precedence. A working agreement fills the gap between "what the organization requires" and "what we, this group, have decided to do."
It also differs from the communication plan. A communication plan might say "weekly status meeting on Tuesdays at 10:00." A working agreement says "we start on time, cameras are optional, and anyone can ask for a topic to be moved to a separate conversation."
| Item | Communication plan | Working agreement |
|---|---|---|
| Focus | Channels, cadence, audiences | Behavior and expectations |
| Example | Status report every Friday | Flag a blocker within one working day |
| Who writes it | Usually the project manager | The whole team |
| Typical length | One page or table | 5 to 8 statements |
Why spend kickoff time on this
Teams rarely fail because someone broke a stated rule. They fail because people held different unstated expectations. One person assumes a chat message needs an answer within minutes. Another assumes the end of the day is fine. Neither is wrong, but the mismatch creates friction that looks like a personality problem.
Writing the expectations down early has three effects:
- It surfaces differences before they cause conflict.
- It gives the team a neutral reference point. "We agreed to flag blockers within a day" is easier to say than "you never tell me when you're stuck."
- It lets new members join with clear expectations instead of guessing.
The topic carries a low weight in the kickoff overall. Spend about five to ten minutes on it in a 60-minute meeting, or run it as a short follow-up session if the agenda is full. The point is a draft the team can accept, not a perfect document.
Areas worth covering
You do not need a rule for everything. Pick the areas where this team is most likely to have mismatched expectations.
- Responsiveness. How quickly people reply on each channel, and what counts as urgent.
- Meetings. Start and end on time, agendas sent ahead, whether laptops and cameras are expected, who takes notes.
- Decisions. Who decides, how the team reaches consensus, and what happens when it cannot. A simple rule is "decide by consensus within the meeting, otherwise the named owner decides within two days."
- Disagreement. How to raise a concern, and where to escalate if the team cannot resolve it.
- Blockers and bad news. When and how to raise them. Many teams agree that early bad news is welcome and late bad news is the problem.
- Availability. Working hours, time zones, planned absences, and handover when someone is out.
- Quality and review. What "done" means, who reviews work, and how fast reviews happen.
- Documentation. Where decisions and files live, so there is a single source of truth.
Writing agreements that work
Weak agreements are vague. "We communicate respectfully" cannot be checked and tells nobody what to do. Strong agreements describe an action, a threshold, or a default.
| Weak | Strong |
|---|---|
| Be responsive | Reply to direct messages within one working day |
| Respect people's time | Meetings start on time and end at the scheduled time or earlier |
| Raise issues early | Flag any task at risk of slipping as soon as you know, in the project channel |
| Make good decisions | Record every decision in the decision log with its owner and date |
| Be open to feedback | Review requests get a first response within two working days |
Use these checks on each draft statement:
- Could a new team member follow it without asking for clarification?
- Could someone observe a breach?
- Is it something this team can actually do given its workload and time zones?
- Does it conflict with a company policy or another agreement?
If a statement fails any check, rewrite it or drop it.
A process for the kickoff
A simple structure keeps this section short and avoids a long debate.
- Frame it (1 minute). Explain what working agreements are and that the goal is a draft, not a final version.
- Individual input (2 minutes). Ask each person to write one or two things that help them work well with a team and one thing that makes it hard. Use sticky notes, a shared document, or the chat.
- Group and propose (3 minutes). The facilitator clusters similar items and reads them out. Turn each cluster into a draft statement.
- Check for agreement (2 minutes). Ask whether anyone cannot live with a statement. Use a thumbs-up, thumbs-down, or sideways-thumb vote. A sideways thumb means "I have a concern but can accept it." Resolve thumbs-down items by editing or removing the statement.
- Record and publish. Add the agreements to the kickoff notes and pin them where the team works.
Asking for individual input first matters. Without it, the loudest or most senior voices set the norms and quieter members stay silent.
A sample set of agreements
The following example uses the same Markdown style as the kickoff notes template. It is a starting point, not a standard. Adjust the numbers to your team.
## Working Agreements: <Project name>
Agreed on: <date> Review on: <date>
1. We reply to direct messages within one working day. Urgent items use a phone call.
2. We flag blockers and risks in the project channel as soon as we know about them.
3. Meetings start on time. Agendas go out 24 hours ahead, and a meeting without an agenda can be declined.
4. We decide by consensus in the meeting. If we cannot, the named owner decides within two working days and records the reason.
5. We log every decision in the decision log with its owner and date.
6. Work is reviewed within two working days of the request.
7. Core hours are 10:00 to 15:00 in each person's own time zone. Planned absences go on the shared calendar.Keeping agreements alive
The most common failure is that the team writes the agreements, files them, and never looks at them again. Three habits prevent this.
- Make them visible. Pin them in the team channel, link them from the project plan, and include them in the onboarding material for new members.
- Schedule a review. Put a check on the calendar for about a month after the kickoff, then at major milestones. Ask which agreements help, which are ignored, and what is missing.
- Apply them without blame. When someone breaks an agreement, refer to the statement and ask what got in the way. The goal is to fix the agreement or the workload, not to punish.
The project manager should also follow the agreements visibly. If the manager sends agendas late or answers messages slowly, the team will conclude the agreements are optional.
Common errors
- Too many rules. A list of 20 items will not be remembered. Keep it to five to eight.
- Rules imposed by the manager. If the team did not help write them, they are instructions, not agreements.
- Vague wording. Statements that cannot be observed cannot be applied.
- Conflicts with reality. A rule like "reply within one hour" fails when half the team works across a nine-hour time difference.
- Ignoring remote participants. In hybrid meetings, collect input in a way remote members can use equally, such as a shared document rather than a physical whiteboard.
- No review. The team's needs change. An agreement that made sense in week one may get in the way by month three.
Exercise
Your team is split across London and Singapore, and one draft agreement says "Everyone responds to chat messages within one hour." Why is this a poor agreement, and how would you rewrite it?
Show answer
It ignores the time difference, so for much of the day the other half of the team is offline and the rule cannot be followed. It also sets a threshold that most knowledge work does not need. A better version is "Reply to chat messages within one working day in your own time zone. For urgent items, use a phone call or tag the message as urgent, and the recipient replies within two hours of their working time." This gives a default, an exception path, and a threshold the team can meet.
Exercise
During the kickoff, the most senior person proposes six rules, and the rest of the team nods. What problem does this create, and what step in the process would you use to correct it?
Show answer
The rules reflect one person's expectations and may not match how the others work, so they are likely to be ignored or resented. Quieter members may have concerns they did not voice. Return to the individual input step: ask everyone to write their own preferences and difficulties before discussing, then group the results and check for agreement with a thumbs vote so that objections become visible.