Following Up at 30, 60, and 90 Days
Assume you understand the kaizen event charter, baseline measures, countermeasures, and standard work. This chapter focuses on keeping the improvement in place after the event. A successful report-out shows that a change worked. Follow-up checks whether people still use it, whether the process still performs, and whether new problems have appeared.
Why follow-up matters
A kaizen event changes a process quickly. Normal work, staff changes, demand changes, and competing priorities can gradually return the process to its old condition. This decline is called backsliding.
Follow-up turns the event result into a management routine. The team compares current performance with the baseline and the target. It also checks whether the new method is practical for the people who use it.
A useful follow-up plan answers four questions:
- Who owns the new process?
- Which measures will be reviewed?
- What evidence shows that standard work is being followed?
- What action will be taken if performance falls below the target?
Build a control plan
A control plan is a short document that connects each important process measure to an owner, review frequency, and response. Keep it visible where the work is managed.
| Item | Example for order entry |
|---|---|
| Primary measure | Median time from order receipt to confirmation |
| Target | 2 hours or less |
| Review frequency | Daily during the first month, then weekly |
| Owner | Order-entry supervisor |
| Reaction plan | Check the queue, identify the cause, and restore the standard method |
Include both outcome measures and process measures. An outcome measure shows whether the customer or business result improved. Lead time and status-inquiry calls are outcome measures. A process measure shows whether the actions that produce the result are happening. Examples include the percentage of orders using the new intake checklist and the number of unassigned orders at each shift change.
The 30-day review
At 30 days, check whether the change has been adopted.
- Compare the latest data with the baseline and target.
- Observe the process instead of relying only on reports.
- Ask operators what makes the standard work difficult.
- Confirm that forms, software settings, visual controls, and training materials still match the process.
- Record exceptions and assign owners for corrective actions.
Do not treat a missed target as proof that the countermeasure failed. First determine whether the team used it consistently and whether the demand or product mix changed.
The 60-day review
At 60 days, test stability. Look for patterns across shifts, teams, locations, or types of work. A process can meet its average target while one shift experiences repeated delays.
Review the trend, not just one favorable result. Confirm that the process owner has incorporated the measure into regular team meetings. Remove temporary event supports only when the process can perform without them. If the standard is unclear or burdensome, revise it with the people doing the work and record the change.
The 90-day review
At 90 days, decide whether the improvement is sustained and whether it should spread.
The event owner should present:
- Baseline, target, and current performance
- Evidence that standard work is being followed
- Remaining gaps and their causes
- Actions that are complete, late, or no longer needed
- A recommendation to sustain, revise, or expand the change
Expansion should follow evidence. A method that works for one product or shift may need adjustment elsewhere.
Exercise
At the 60-day review, the median lead time remains below target, but the night shift has frequent delays. What should the team do?
Show answer
Review the night-shift process, observe how the standard work is applied, identify the cause of the variation, and assign a corrective action. Do not approve expansion based only on the overall median.