Threats and opportunities: two sides of risk
Prerequisites
This chapter assumes you know basic project vocabulary (scope, schedule, budget, stakeholders), what a risk is, and how probability and impact are rated on a 1 to 5 scale.
Threats and opportunities: two sides of risk
A threat is a risk with a negative effect, such as a supplier delivering late. An opportunity is a risk with a positive effect, such as a customer ordering early for a discount. Both need planned responses, but the goals differ. You reduce threats and increase opportunities.
From probability and impact to a risk score
Multiply probability (1 to 5) by impact (1 to 5) to get a score from 1 to 25. A threat with probability 3 and impact 4 scores 12. Scores rank risks, so you can spend effort on the highest ones first.
Risk appetite and thresholds
Risk appetite is how much uncertainty an organization will accept to pursue its goals. A threshold is the score at which a risk needs a planned response. With a threshold of 10, any risk scoring 10 or more gets a response, and lower scores are monitored only. Risks beyond the project's authority go up to the sponsor.
Planning responses and assigning risk owners
Every risk above the threshold needs a response strategy and one named owner who is accountable for it. Without an owner, a planned response often never happens. Record the owner beside the strategy so the decision and its accountability stay together.
Avoiding a threat
Avoidance removes a threat by changing the plan so the threat cannot occur. For example, a team could choose a supplier with local stock, so late shipping is no longer possible. Avoidance is the strongest response, but it often costs scope, time, or money.
Transferring a threat
Transfer shifts the financial impact or ownership of a threat to a third party, usually through insurance or a contract with penalty clauses. Transfer does not remove the threat. The supplier may still be late, but the contract covers the cost of the delay. Transfer usually has a fee, so compare that fee with the expected impact.
Exercise
A threat has probability 2 and impact 5, and the threshold is 10. Does it need a planned response, and why?
Show answer
Yes. Its score is 2 x 5 = 10, which meets the threshold of 10, so it needs a response strategy and an owner.