Accepting an opportunity
This chapter assumes you know how probability and impact combine into a risk score, can name a risk owner, and understand the difference between a threat and an opportunity.
Accepting an opportunity
Accepting an opportunity means the team takes no active step to pursue it, or only a light one. Passive acceptance means the team watches for the opportunity and takes the benefit if it arrives. Active acceptance means the team sets aside time or money in advance, such as a reserved schedule slot, so it can capture the benefit quickly.
Escalating risks outside the project's authority
Some risks exceed the project manager's authority. They may threaten the business case, need funds beyond the approved budget, or affect other projects. Escalate these to the sponsor or portfolio board with a short summary: the risk, its score, the options, and a recommended response. Escalation applies to threats and opportunities alike.
Choosing the right strategy for a risk
Start with the score, then compare it with the risk appetite threshold. Ask two more questions: does the response cost less than the exposure it removes, and does the project have authority to act? Threats receive avoid, transfer, mitigate, or accept. Opportunities receive exploit, share, enhance, or accept. Anything beyond the project's authority goes to escalation.
Contingency plans, fallback plans, and triggers
A contingency plan is the response the team runs when a defined trigger occurs. A trigger is an observable signal, such as a supplier missing its first confirmed shipping date. A fallback plan is a second response used if the contingency fails. Define triggers in measurable terms so the team knows exactly when to act.
Contingency and management reserves
A contingency reserve is time or money the project manager holds for known risks. A management reserve is held by the sponsor or governance body for unknown risks outside the project baseline. Size reserves from the risk analysis, and approve their use through an agreed route.
Residual and secondary risks
A residual risk remains after a response is applied. A secondary risk arises because of the response. For example, a second supplier removes single-source dependency but may have unproven quality. Record both, and give each its own owner.
Recording responses in the risk register
Each entry should include the ID, description, type, score, strategy, response, owner, trigger, contingency, residual and secondary risks, and status. Clear owners and triggers let someone act without waiting for a decision.
Monitoring whether responses work
Review triggers at each status meeting. After a response runs, re-score the risk and compare the new score with the target. If the response does not lower exposure or does not help capture the opportunity, change the response and update the register.
Exercise
Exercise
A team accepts an opportunity passively. What is one step that would make the acceptance active?
Show answer
Set aside a small reserve of time or budget, or name an owner who can act quickly when the opportunity appears.