Sub topic 2
Mitigating a threat
This chapter assumes you can score a risk by probability and impact, and that you know what a risk owner does. It covers responses to threats (negative risks) and opportunities (positive risks) after the analysis step.
Mitigating a threat
Mitigation reduces the probability, the impact, or both, of a threat. The risk stays on the register, but its exposure drops. For example, a key supplier may deliver payment terminals late. The team orders a first batch early and qualifies a second supplier. Both actions lower the chance of delay or limit its effect.
Mitigation often creates a secondary risk. The second supplier's quality may be unproven.
ID: R-07
Type: Threat
Description: Key supplier may deliver the payment terminals late.
Probability: Medium (3/5) Impact: High (4/5) Score: 12
Strategy: Mitigate
Response: Order a first batch early and qualify a second supplier.
Owner: Procurement lead
Trigger: Supplier misses the first confirmed shipping date
Residual risk: Second supplier's quality is unproven (secondary risk R-15)
Status: OpenAccepting a threat
Acceptance means the team takes no action to change a threat's probability or impact. It has two forms.
Passive acceptance
The team records the risk and deals with it only if it occurs. No contingency money or plan is prepared in advance. This suits low-score risks.
Active acceptance
The team records the risk and prepares a contingency plan. The plan names a trigger, a fallback action, and a reserve to pay for it.
Exploiting an opportunity
Exploit makes an opportunity certain to happen. The team adds resources or changes its approach. For example, a team may assign its best engineers to finish a feature early so that a customer's early-adopter discount applies.
Sharing an opportunity
Share gives part of the gain to a partner better placed to capture it. The team might form a joint venture or a revenue-sharing agreement. It accepts a smaller share of the benefit in return for a higher chance of capturing the rest.
Enhancing an opportunity
Enhance raises an opportunity's probability or impact by strengthening its causes. Suppose a larger customer may adopt the pilot early. The team offers an early-adopter incentive and schedules a demo for the customer's decision makers.
| Type | Strategy | Effect on the risk |
|---|---|---|
| Threat | Mitigate | Lowers probability or impact |
| Opportunity | Enhance | Raises probability or impact |
Exercise
A threat scores 6, and the threshold is 10. Which response fits best, and why?
Show answer
Accept it. Its score is below the threshold, so the team records it and spends no effort on mitigation. Passive acceptance is enough unless the team judges that a contingency plan is worth its cost.