Sub topic 3
Run and Monitor the Pilot
This chapter assumes you know cycle time, defect rate, and throughput. It also assumes you can compute a mean and spread for a data set, and that you already have a written hypothesis with guardrail metrics.
Run and Monitor the Pilot
Run the pilot exactly as the plan describes. Log every deviation, such as a missed training session or a supplier delay, because these events explain later anomalies. Check the guardrail metrics on a fixed schedule, daily for high-risk changes and weekly otherwise. Do not change the target or the decision rule while the pilot runs.
Analyze the Results
Compare the pilot group with the control group on the metric named in your hypothesis. Then ask whether the difference is larger than normal random variation. The permutation test below shuffles the group labels 10,000 times and counts how often a random split shows a reduction at least as large as the observed one.
import random
from statistics import mean
control = [42, 45, 39, 48, 44, 41, 46, 43] # cycle time in minutes, current process
pilot = [36, 38, 35, 40, 37, 34, 39, 36] # cycle time in minutes, changed process
observed = mean(control) - mean(pilot)
random.seed(1)
combined = control + pilot
n_control = len(control)
trials = 10000
extreme = 0
for _ in range(trials):
random.shuffle(combined)
diff = mean(combined[:n_control]) - mean(combined[n_control:])
if diff >= observed:
extreme += 1
print(f"Mean reduction: {observed:.2f} minutes")
print(f"Share of random splits at least as extreme: {extreme / trials:.4f}")A small share suggests the reduction is unlikely to come from chance alone. A large share means the pilot did not show a clear effect. Also check whether the reduction is big enough to matter in practice.
Avoid Common Pilot Pitfalls
- Peeking: Checking results daily and stopping when they look good inflates false positives.
- Selection bias: Choosing the strongest team as the pilot site overstates the gain.
- Novelty effect: Early gains often fade once the team stops paying extra attention.
- Confounding: Changing two things at once makes it impossible to credit either one.
Decide: Go, Adjust, or Stop
Apply the rule agreed before the pilot. Stop and roll back if a guardrail is breached, whatever the gain. Go if the target is met. Adjust if the process is safe but the target is missed.
Record the decision, the data behind it, and the reason in a short document.
Scale Up and Standardize
Update the standard work, train the remaining sites, and keep the guardrail monitoring in place after rollout. Schedule a review to confirm the gains hold at the new scale.
Exercise
Exercise
A pilot cuts cycle time by 12 percent, but the defect rate rises above the agreed limit. What is the decision?
Show answer
Stop and roll back. A guardrail breach overrides any improvement in the target metric.