Sub topic 2
Design a fair comparison
This chapter assumes you know cycle time, defect rate, and throughput, and that you can read a mean and a range from a data set. You will set up a comparison that shows whether the change caused any difference in results.
Design a fair comparison
Compare the pilot group with a control group that runs the current process at the same time. Choose both groups from similar shifts, products, or sites so that seasonal load and staffing do not explain the difference. Assign work by a rule you write down before the pilot starts. Do not let people pick the easiest cases for the pilot.
Set duration and sample size
Run the pilot long enough to cover normal variation, such as at least two full weekly cycles. Estimate the sample size before you start. The following function gives a rough per-group count for a two-sided test at 5% significance and 80% power.
import math
def runs_per_group(sd, target_change, z_alpha=1.96, z_power=0.84):
"""Rough per-group sample size for a difference in means."""
n = 2 * ((z_alpha + z_power) * sd / target_change) ** 2
return math.ceil(n)
print(runs_per_group(sd=4.0, target_change=3.0)) # 28Set guardrails and a rollback plan
Guardrail metrics are safety limits that must hold even when the main metric improves. Set each limit, the action it triggers, and the person who can trigger it before the pilot starts.
| Guardrail | Limit | Action if breached |
|---|---|---|
| Defect rate | Above 3% | Stop pilot and revert to current process |
| Rework hours per day | More than 10% above baseline | Pause and review with the team |
| Overdue orders | More than 5 points above baseline | Pause and review |
Prepare the people involved
- Tell operators what changes, why it changes, and what stays the same.
- Train the pilot team and one backup person on the new steps before the first day.
- Name one owner who can call a rollback.
- Brief the control group so it keeps running the current process without changes.
Plan data collection
Define each metric, its unit, who records it, and where. Record both groups at the same point in the process, and use the same definitions in the baseline and the pilot.
Exercise
Your target is a 3-minute cycle time reduction, and cycle time has a standard deviation of 4 minutes. Using the function above, how many runs does each group need?
Show answer
28 runs per group. The calculation is 2 × ((1.96 + 0.84) × 4 / 3)² = 27.9, which rounds up to 28.