Sub topic 11
Reviewing estimates against actual time
This chapter assumes you can already make a baseline estimate and set a self-imposed deadline with a buffer. Here you close the loop. You compare what you predicted with what happened, and you use the gap to set better deadlines next time.
Why review at all
Your first estimates will run optimistic because of the planning fallacy. A fixed buffer, such as 25%, is a guess about how wrong you are. A review replaces that guess with your own data.
Reviewing also guards against Parkinson's law in the other direction. If every task finishes exactly on its deadline, you can't tell whether the deadline was right or whether the work simply stretched to fit it. Recording actual time shows which one happened.
Record two numbers per task
For each finished task, write down:
- The estimate, in hours, made before you started.
- The actual focused time, in hours, measured while you worked.
Record the estimate before you start. If you write it afterward, memory will quietly move it toward the real result. Track focused time, not elapsed calendar time, so that waiting and interruptions don't distort the figures.
| Task | Estimated (h) | Actual (h) | Ratio |
|---|---|---|---|
| Draft report | 2 | 3 | 1.5 |
| Prepare slides | 5 | 6 | 1.2 |
| Fix formatting | 1 | 1.5 | 1.5 |
Compute a calibration ratio
Divide total actual time by total estimated time. A value above 1 means your estimates run low. A value below 1 means they run high.
Use totals, not an average of the per-task ratios. Totals weight large tasks more heavily, and one tiny task with a wild ratio can't dominate the result.
def calibration_ratio(history):
"""history is a list of (estimated_hours, actual_hours) pairs."""
total_estimated = sum(estimated for estimated, _ in history)
total_actual = sum(actual for _, actual in history)
return total_actual / total_estimated
history = [(2, 3), (5, 6), (1, 1.5)]
print(round(calibration_ratio(history), 2))The output is 1.31. The totals are 8 estimated hours against 10.5 actual hours, so your estimates run about 31% low.
Feed the ratio back into the next deadline
Multiply a new baseline estimate by the ratio before you add any other padding. A 10-hour estimate becomes about 13 hours. You can then use self_deadline from the earlier chapter with the corrected figure.
from datetime import date, timedelta
from math import ceil
def self_deadline(start, estimate_hours, hours_per_day=4, buffer=0.25):
"""Return a calendar-day deadline from a baseline estimate plus a buffer."""
padded_hours = estimate_hours * (1 + buffer)
days_needed = ceil(padded_hours / hours_per_day)
return start + timedelta(days=days_needed)
ratio = 1.31
corrected = 10 * ratio
print(self_deadline(date(2026, 3, 2), estimate_hours=corrected))With the ratio applied, the deadline moves from 4 days out to 5 days out, because 13.1 hours plus a 25% buffer is about 16.4 hours, and that is 5 days at 4 hours a day.
The review loop
Run the review at a regular point, such as the end of each week. Five to ten finished tasks is enough to start. Keep the history rolling, so the ratio reflects your recent habits and not your habits from a year ago.
Common errors
- Reviewing only the misses. If you log only the tasks that overran, the ratio will look worse than it is. Log every task.
- Mixing task types. Writing and administrative chores may have different ratios. If the gap is large, keep a separate ratio for each type.
- Too little data. A ratio from two tasks is noise. Treat it as a hint until you have more.
- Blaming yourself. A ratio of 1.3 is a measurement, not a verdict. Adjust the plan, not your opinion of yourself.
- Ignoring the low side. If the ratio is well below 1 and tasks finish early, your deadlines may be loose enough to invite stretching. Tighten them a little.
Exercise
Your history is [(4, 5), (2, 2), (6, 9)]. Compute the calibration ratio, then say what focused-hour estimate you should use for a new task you first estimated at 8 hours.
Show answer
Total estimated is 12 hours and total actual is 16 hours, so the ratio is 16 / 12 ≈ 1.33. Multiply the new baseline by it: 8 × 1.33 ≈ 10.7 hours. Use about 10.7 focused hours, and keep any extra buffer small so you don't pad twice.