Defining done before you set a date
This chapter assumes you know how to keep a to-do list and have worked on tasks with due dates. It also assumes you have seen the earlier chapters on why work stretches to fill the time it is given.
Why done comes before the date
Parkinson's law says work expands to fill the time available. A vague task expands the most. If "write the report" has no clear end, you can always add another section, reread it once more, or polish the formatting. No date can stop that, because nothing says the work is finished.
A definition of done is a short, checkable statement of what must be true for a task to count as complete. You write it before you estimate or set a deadline. The estimate in the next chapter is only as good as the definition it measures.
What a good definition looks like
A good definition is observable. Another person could check it, or you could check it on a tired Friday afternoon without arguing with yourself. It describes the result, not the effort.
Compare these pairs:
| Vague | Checkable |
|---|---|
| Work on the budget | Budget spreadsheet has one row per category and totals match the bank export |
| Prepare the talk | Ten slides exist, and I have rehearsed once aloud with a timer under 15 minutes |
| Clean up the code | Linter reports zero warnings and existing tests pass |
| Research vendors | A table compares three vendors on price, support, and contract length |
Words like "work on", "look into", and "prepare" describe activity. Activity has no natural stopping point. Words like "exists", "passes", and "contains" describe states you can verify.
Writing one in four steps
- Name the deliverable. State what will exist when you finish: a document, a merged change, a sent email.
- List the checks. Write two to five conditions that must hold. Keep each one yes-or-no.
- Set the quality bar. Decide the level of polish you need. "Good enough to send to my manager for a first read" is a different bar from "ready to publish".
- Write what is out of scope. List things you might be tempted to add and are choosing not to do. This is your guard against expansion.
A worked example
Suppose your task is "Update the team onboarding guide." Left like that, it could take an hour or a week.
Rewrite it with a definition of done:
- Deliverable: The onboarding guide in the shared folder, revised.
- Checks:
- The setup steps match the current tool versions.
- Every broken link is fixed or removed.
- One new hire has read it and reported no blocking questions.
- Quality bar: Accurate and readable. Formatting stays as it is.
- Out of scope: Redesigning the layout, adding a glossary, rewriting the history section.
Now you can estimate. Checking setup steps and links is a few hours. The new-hire read adds waiting time, which you can see only because the check exists. A vague task hides that dependency until late.
You can also keep the checks as data. This small script reports whether a task is done and what remains:
def remaining_checks(checks):
"""checks maps each check's description to True (passed) or False."""
return [name for name, passed in checks.items() if not passed]
onboarding = {
"Setup steps match current tool versions": True,
"Broken links fixed or removed": True,
"New hire read it with no blocking questions": False,
}
left = remaining_checks(onboarding)
print("Done" if not left else f"Not done: {left}")The output is Not done: ['New hire read it with no blocking questions']. You do not need code for this in practice. The point is that done is a yes-or-no state computed from the checks.
Common errors
- Defining done as time spent. "Work on it for two hours" is a timebox, which is a different tool covered later. It caps effort but does not say what the result is.
- Writing checks you cannot verify. "The summary is excellent" invites endless revision. Replace it with something observable, such as "A colleague can state the main recommendation after reading it."
- Setting the bar too high. Every extra check lengthens the task. If your definition describes a perfect result, the estimate will be inflated, and Parkinson's law will fill it.
- Changing the definition midway. Adding checks after you start is scope creep. If you find a real gap, record it as a new task.
Exercise
Rewrite the task "Improve the website homepage" with a deliverable, three checkable conditions, and one out-of-scope item.
Show answer
One valid answer. Deliverable: the revised homepage live on the site. Checks: (1) the page loads in under three seconds on the test connection, (2) the signup button appears above the fold on a laptop screen, (3) a colleague finds the pricing link in under ten seconds. Out of scope: redesigning the navigation menu. Any answer is acceptable if each check can be answered yes or no by someone else.
Exercise
Why does a definition of done make a deadline more effective against Parkinson's law?
Show answer
Without it, the task has no clear end, so extra time gets absorbed by optional polishing and rechecking. A definition of done marks the point where the work is finished, so a deadline limits the work to that scope instead of just the time.