Sub topic 4
What NPV Measures
Prerequisites and purpose
This chapter assumes you can enter Excel formulas, use cell references and ranges, and work with percentages and compound interest. You should also understand that a cash outflow is usually shown as negative and a cash inflow as positive.
Net present value (NPV) measures the value created by a series of future cash flows after converting them to today's money. It answers this question:
> After allowing for the required return, how much value does this project add or destroy today?
The time value of money
A dollar available today is worth more than a dollar received later. You can invest today's dollar, while a future dollar cannot be used until it arrives. Inflation, risk, and alternative investments also affect what future cash flows are worth today.
A discount rate is the required return used to convert future cash flows into present value. For a cash flow received in period \(t\), the present value is:
\[ PVt = \frac{CFt}{(1+r)^t} \]
Here, CF is the cash flow, r is the discount rate per period, and t is the number of periods from today.
NPV adds the present value of every cash flow:
\[ NPV = \sum{t=0}^{n}\frac{CFt}{(1+r)^t} \]
The period-zero cash flow is today, so its denominator is 1. An initial investment is therefore included at its full negative amount.
Worked example
Suppose a project requires $10,000 today and produces the following annual cash flows. Use an 8% discount rate.
| Period | Cash flow | Present value at 8% |
|---|---|---|
| 0 | -$10,000 | -$10,000.00 |
| 1 | $3,000 | $2,777.78 |
| 2 | $4,000 | $3,429.36 |
| 3 | $4,000 | $3,175.33 |
| 4 | $3,000 | $2,205.03 |
The future cash flows have a combined present value of about $11,587.50. After subtracting the $10,000 investment:
\[ NPV \approx \$1,587.50 \]
A positive NPV means the project is expected to earn more than the required 8% return. A negative NPV means it earns less than that required return. An NPV of zero means the project exactly meets the required return.
Interpreting the discount rate
The discount rate must match the cash flows:
- Use an annual rate for annual cash flows.
- Use a monthly rate for monthly cash flows.
- Include the return required for the project's risk and financing context.
- Do not mix nominal rates, effective rates, and cash-flow periods without converting them.
The discount rate is a modeling assumption, not a universal property of the project. Changing it changes the NPV. A higher rate reduces the present value of distant cash flows and usually lowers NPV.
Exercise
A project costs $5,000 today and returns $3,000 at the end of each of the next two years. At a 10% discount rate, is its NPV positive or negative?
Show answer
NPV = -5,000 + 3,000 / 1.10 + 3,000 / 1.10^2 = about $206.61, so it is positive.