NPV versus IRR in Project Decisions
Assume you know basic Excel ranges, percentages, compound interest, and date entry. You should also know how to lay out cash flows by period and use NPV, IRR, XNPV, and XIRR.
Two measures, two decision questions
Net present value (NPV) measures how much value a project adds today after discounting its future cash flows at a required return. The required return is the minimum return acceptable for the project, often called the hurdle rate.
Internal rate of return (IRR) is the discount rate that makes a project’s NPV equal to zero. It expresses the project’s result as a percentage per period.
NPV = present value of future cash flows - initial investment
IRR = rate where NPV equals zeroFor an independent project, the usual rules are:
- Accept the project when NPV is greater than zero.
- Reject the project when NPV is less than zero.
- Accept the project when IRR is greater than the hurdle rate.
- Reject the project when IRR is less than the hurdle rate.
These rules agree when the project has conventional cash flows, such as one initial outflow followed by inflows.
Why NPV usually leads
NPV measures value in currency. An NPV of $25,000 means the project adds $25,000 of present value at the selected discount rate. This makes NPV useful when comparing the total contribution of projects.
IRR measures return as a percentage. It can favor a small project with a high percentage return over a larger project that creates more total value. It can also rank projects differently when their cash flows arrive at different times.
For mutually exclusive projects, you can choose only one. If NPV and IRR disagree, use NPV when the discount rate is reliable and the objective is to maximize value.
| Situation | Preferred measure | Reason |
|---|---|---|
| Independent project | NPV or IRR | Both usually give the same accept or reject result |
| Mutually exclusive projects | NPV | Measures total value added |
| Irregular dates | XNPV and XIRR | Uses actual dates |
| Unusual cash-flow signs | NPV or MIRR | IRR may have multiple or no meaningful solutions |
A decision workflow
For dated cash flows, use XNPV and XIRR rather than periodic functions. XNPV uses the actual number of days between dates, with a 365-day basis. XIRR produces an annualized rate.
When IRR can mislead
IRR assumes that interim cash flows can be reinvested at the IRR itself. That assumption may be unrealistic when the IRR is very high. IRR can also produce multiple answers when cash-flow signs change more than once. In other cases, Excel may return #NUM! because it cannot find a solution from its starting guess.
MIRR offers an alternative. It discounts negative cash flows at a finance rate and compounds positive cash flows at a reinvestment rate. This makes the assumptions explicit.
Exercise
Project A costs $100,000 and has an NPV of $18,000. Project B costs $200,000 and has an NPV of $25,000. If you can choose only one project, which project should normally be preferred?
Show answer
Project B, because it creates the greater positive NPV. IRR should be used as supporting information, not as the primary ranking measure.