The NPV Timing Pitfall: Adding the t=0 Cash Flow
Prerequisites and the timing rule
This chapter assumes that you can enter Excel formulas, use cell ranges, work with percentages, and distinguish today from a future period.
Net present value (NPV) measures the value today of future cash flows after discounting them at a required rate of return. Excel's NPV function assumes that the first value in its range arrives at the end of the first period. It does not treat the first value as a cash flow occurring today.
A cash flow at time zero, written as t=0, occurs immediately. It needs no discounting. Therefore, keep it outside the NPV range and add it separately.
Discount rate: B1 = 8%
B3 = -10000
B4 = 3000
B5 = 4000
B6 = 4000
B7 = 3000
Correct NPV:
=NPV(B1, B4:B7) + B3The formula discounts the cash flows in B4:B7 for one through four periods. It then adds the initial outflow in B3 at its full value.
Why the first value is discounted
For periodic cash flows, the mathematical NPV formula is:
\[ NPV = CF0 + \frac{CF1}{(1+r)^1} + \frac{CF_2}{(1+r)^2} + \cdots \]
Here, CF0 is the time-zero cash flow and r is the discount rate. Excel's NPV(rate, value1, value2, ...) calculates only the discounted terms beginning with CF1.
The common error
This formula is usually wrong when B3 is the initial investment:
=NPV(B1, B3:B7)Excel treats B3 as a period-one cash flow. It divides -10000 by 1.08, instead of leaving it at -10000. The formula therefore shifts every cash flow one period later than intended.
| Formula | Treatment of B3 | Result |
|---|---|---|
| `=NPV(B1,B4:B7)+B3` | Today, with no discounting | Correct |
| `=NPV(B1,B3:B7)` | End of period one | Incorrect for a t=0 outflow |
Checking the result
A useful cross-check is to calculate the discounted cash flows manually or with SUMPRODUCT:
=B3 + B4/(1+B1)^1 + B5/(1+B1)^2 + B6/(1+B1)^3 + B7/(1+B1)^4This value should match:
=NPV(B1, B4:B7) + B3If the two formulas disagree, inspect the period labels, signs, discount rate, and whether the first cash flow really occurs at time zero.
Exercise
If the initial investment is in B3 and future cash flows are in B4:B7, which formula correctly calculates NPV at the discount rate in B1?
Show answer
=NPV(B1, B4:B7) + B3