Sub topic 11
Reviewing and adjusting your plan
This chapter assumes you have kept an energy log for one to two weeks, sorted your tasks by the energy they demand, and drafted a daily template that puts demanding work in your high-energy hours. You should be comfortable running a short Python script. The goal now is to check whether the plan works and to change it using evidence instead of mood.
Why a first plan needs a review
A schedule built from one or two weeks of log data is a hypothesis. It can be wrong in several ways:
- The log covered an unusual stretch, such as a deadline week or a week with a cold.
- Your ratings drifted as you got used to the scale.
- The plan works on paper but collapses against real meetings.
- Your pattern has changed since you collected the data. Shifts in season, workload, or sleep can do this.
A review is a short, scheduled check that compares what the plan predicted with what happened. Without one, you tend to do one of two things. You abandon the plan after one bad day, or you follow it for months after it stopped fitting.
What to review
Look at three things each time. Each one answers a different question.
| Question | Evidence | What a problem looks like |
|---|---|---|
| Is my energy pattern still what I think it is? | Recent log entries, averaged by hour | A "high" hour now averages 3 or lower, or a "low" hour averages 4 or higher |
| Did I follow the plan? | Calendar and task list | Demanding work keeps landing outside the high-energy block |
| Did the plan help? | Finished tasks, quality of output, how the day felt | Peak hours are protected but the important work is still not finished |
Keep these separate. A plan can fail because the pattern is wrong, because you did not follow it, or because the pattern and the plan are both fine and something else is limiting your output, such as unclear tasks or too much work. Fixing the schedule will not help with the last case.
A weekly review routine
Pick a fixed slot, ideally in a low-energy period, since a review is routine work. Friday afternoon or Monday before the first meeting both work. Fifteen minutes is enough.
- Update the log so that the last week is complete. Fill in gaps from memory only the same day, and mark late entries if you can.
- Run the hourly-average comparison (below) and read the output.
- Check the calendar. Count how many demanding tasks were done in high-energy hours.
- Write one sentence about what worked and one about what did not.
- Choose at most one change for next week. Write it down.
The limit of one change is deliberate. If you move your deep-work block, drop a meeting, and change your lunch time all at once, you cannot tell which change helped.
Comparing recent data with earlier data
The log format from earlier in this tutorial has four columns: date, hour, energy, task. The script below splits the log into the most recent seven days and everything before that, then prints the average energy for each hour in both periods. It marks an hour when the averages differ by at least one point and both periods have enough entries to be worth comparing.
import csv
from collections import defaultdict
from datetime import date, timedelta
LOG_FILE = "energy_log.csv"
RECENT_DAYS = 7
MIN_ENTRIES = 3 # fewer entries than this in either period: do not trust the comparison
MIN_CHANGE = 1.0 # smallest difference in average energy worth acting on
def load_log(path):
rows = []
with open(path, newline="") as f:
for row in csv.DictReader(f):
rows.append(
(date.fromisoformat(row["date"]), int(row["hour"]), int(row["energy"]))
)
return rows
def hourly_scores(rows):
scores = defaultdict(list)
for _, hour, energy in rows:
scores[hour].append(energy)
return scores
def main():
rows = load_log(LOG_FILE)
if not rows:
print("The log is empty.")
return
latest = max(d for d, _, _ in rows)
cutoff = latest - timedelta(days=RECENT_DAYS - 1)
earlier = hourly_scores([r for r in rows if r[0] < cutoff])
recent = hourly_scores([r for r in rows if r[0] >= cutoff])
print(f"Recent period: {cutoff} to {latest}")
for hour in sorted(set(earlier) | set(recent)):
old, new = earlier.get(hour, []), recent.get(hour, [])
if not old or not new:
print(f"{hour:02d}:00 not present in both periods")
continue
old_avg = sum(old) / len(old)
new_avg = sum(new) / len(new)
change = new_avg - old_avg
enough = len(old) >= MIN_ENTRIES and len(new) >= MIN_ENTRIES
if not enough:
flag = "too few entries"
elif abs(change) >= MIN_CHANGE:
flag = "CHANGED"
else:
flag = "stable"
print(
f"{hour:02d}:00 earlier {old_avg:.1f} ({len(old)}) "
f"recent {new_avg:.1f} ({len(new)}) {change:+.1f} {flag}"
)
main()The numbers in parentheses are entry counts. They matter more than they look. An average of 4.0 built from one entry is a single rating, not a pattern.
The thresholds are judgment calls. A one-point difference on a five-point self-rating is roughly the smallest change you can distinguish from day-to-day noise, and only if you have several entries behind it. If you log every hour, MIN_ENTRIES = 3 is easy to meet. If you log only a few times a day, you may need two or three weeks of recent data before any hour qualifies.
Reading the results
A CHANGED flag tells you to look closer, not to move your schedule. Before you act, check these in order.
Is it a real shift or an unusual week?
Look at the daily entries behind the average. If one bad day pulled the average down, such as a night with little sleep, that is an outlier. Consider leaving the plan alone and watching another week. If the drop appears on most days, it is more likely a real change.
Is something else explaining it?
Several factors move your energy without changing your underlying rhythm:
- Sleep debt from a short week.
- Illness, travel, or time-zone changes. Daylight saving changes can also shift how mornings feel for a couple of weeks.
- A heavy meeting load that leaves you tired by early afternoon.
- A change in caffeine, meals, or exercise timing.
If an obvious cause exists, treat the change as temporary. Note it in the log's task column or in a separate notes file so that you can discount those days later.
Is the problem the plan, or the execution?
A low rating in your protected morning block may mean your energy fell. It may also mean you spent that block on messages and your rating reflected the task, not the time of day. Compare ratings for the same hour across different tasks. If 9:00 scores 5 when you write and 2 when you answer email, the hour is not the problem.
Choosing an adjustment
Match the adjustment to the finding. The smallest change that addresses the problem is usually the right one.
| Finding | Reasonable adjustment |
|---|---|
| Peak hours have shifted by an hour or more | Move the deep-work block by the same amount, then watch for a week |
| Peak block is the same, but it keeps getting interrupted | Block the calendar, silence notifications, and move optional meetings out of it |
| Peak block feels shorter than planned | Shorten it. Two focused hours beat a nominal four |
| Low-energy block is also unusually low | Add a break or a walk, and check sleep and lunch before changing tasks |
| A task type does not fit its slot | Reclassify the task and keep the slot |
| Plan followed, but important work is unfinished | Reduce the commitments. The schedule cannot create more hours |
| Ratings are flat, with every hour near 3 | Check whether you are rating consistently before drawing conclusions |
Ratings that stop being informative
Self-ratings can lose their usefulness. If every entry becomes a 3 because you rate without thinking, the log carries no signal. Re-anchor the scale by writing one-line definitions, for example: 5 means you could start a hard problem without effort, 3 means you can work but need to push, 1 means you are reading the same line repeatedly. If the problem persists, pause the log for a month and resume later with a one-week check.
Knowing when to stop adjusting
Reviewing can become its own time sink. Some guidelines:
- Move to a monthly review once the weekly comparison shows
stablefor most hours across three weeks in a row. - Return to a weekly review after a disruption: new job, new baby, new shift, an extended illness, or a season change.
- Do not rearrange the plan because of a single day. Decide in advance what counts as evidence, such as a flagged change that appears in two consecutive reviews.
- Keep a short changelog: date, change, and reason. When something later goes wrong, you can see what you changed and undo it.
Common review mistakes
- Reacting to one day. One poor night produces one poor morning. That is not a shifted pattern.
- Reviewing only the energy data. A plan can match your energy perfectly and still fail because you never defended the block.
- Chasing the average. Averages hide variance. If 14:00 is sometimes 5 and sometimes 1, find out what separates those days.
- Skipping reviews when things go well. A good week is also data. Note what you did.
- Treating the schedule as a rule. If a task is urgent and your peak hour is gone, do it anyway and accept the cost. The plan is a default, not an obligation.
Exercise
Your comparison script prints "09:00 earlier 4.5 (8) recent 3.0 (2) -1.5 too few entries". Should you move your deep-work block out of the 09:00 hour? Give your reasoning and name the next step.
Show answer
Not yet. The recent period has only two entries, below the minimum of three, so the drop could come from one or two unusual days. The next step is to look at those two entries and the notes for those days for an obvious cause such as poor sleep. Then keep logging for another week. If the 09:00 average stays low across at least three recent entries, and the cause is not temporary, move the block by one hour and watch the result.
Exercise
After two weeks of review, you find that your plan places deep work at 09:00-11:30, you rate 09:00 and 10:00 at 4 or 5 on most days, and yet you finish little deep work. The calendar shows that standing meetings fall in that block on three days a week. What is the most appropriate single change for next week, and why only one?
Show answer
Protect the block from the standing meetings, for example by moving or declining the meetings on those days, or by moving them to a medium-energy slot. The energy data is fine, so the schedule's timing does not need to change. The failure is in execution. Making only this change means that any improvement in finished deep work can be attributed to it, and you avoid mixing it with changes to timing, breaks, or task classification.