Sub topic 7
Reading the Handoffs Between Lanes
Assume you already know basic flowcharts, the process you want to improve, and the difference between processing time and waiting time. This chapter focuses on reading what happens when work crosses from one swimlane to another.
What a handoff means
A handoff occurs when responsibility, information, or a work item moves from one actor to another. The actors may be people, teams, roles, departments, or information systems. In a swimlane diagram, a handoff is usually an arrow that crosses a lane boundary.
A handoff is more than the end of one activity and the start of another. It is a point where the receiving actor must understand what to do, obtain the needed information, and accept responsibility for the next step. Each handoff can create waiting, misunderstanding, duplicate work, or rework.
Do not assume that every handoff is waste. A specialist may need to review a request, or a control function may need to approve a payment. The improvement question is whether the handoff adds enough value to justify its delay and risk.
How to read a handoff
Trace each arrow that crosses a lane boundary and ask five questions:
- What exactly is being transferred?
- What information or quality standard must accompany it?
- Who accepts responsibility after the transfer?
- Where does the work wait?
- What happens when the receiving actor cannot proceed?
The answer may reveal that the visible activity is not the real problem. For example, “Review request” may take two minutes, but the request may wait eight hours in a shared inbox before anyone starts. The handoff is the point where that queue forms.
Record the transfer separately from the activities around it. This keeps the map from hiding delays inside vague labels such as “send to team” or “process by department.”
| Handoff observation | Possible effect | Evidence to collect |
|---|---|---|
| Work waits in a shared queue | Longer lead time | Arrival and start timestamps |
| Required fields are missing | Back-and-forth rework | Rejection or return count |
| Ownership is unclear | Requests are ignored or duplicated | Interview notes and queue history |
| Several channels are used | Information is lost or copied | Email, ticket, and system records |
| A specialist receives every case | Bottleneck at one lane | Volume, capacity, and backlog |
Distinguishing delay, risk, and rework
A handoff creates delay when work waits before the next actor begins. Measure the wait from the time the sender completes the transfer to the time the receiver starts work.
A handoff creates risk when information can be changed, lost, misunderstood, or accessed by the wrong person. Look for manual transcription, informal email instructions, unclear approval limits, and missing audit records.
A handoff creates rework when the receiver sends the item back, asks for clarification, or performs work that the sender already completed. Draw the return arrow explicitly. A loop often explains why the process takes longer than its individual activities suggest.
Count both the number of handoffs and the quality of each handoff. A short process with one poor transfer may perform worse than a longer process with clear interfaces.
Validating what the map shows
Walk through each handoff with both the sending and receiving actors. Ask them to describe the last real case, not the procedure they believe should occur. Compare the answers about:
- The event that marks completion for the sender
- The event that starts work for the receiver
- The information required to begin
- The normal queue or waiting location
- The common reasons for return or escalation
If the two lanes give different answers, preserve that difference in the current-state map. It is useful evidence, not a mapping failure.
Improving a handoff
After validating the current state, compare alternatives:
- Remove the transfer if the work can be completed by the original actor without added risk.
- Move the decision closer to the work when the receiving team adds no specialist judgment.
- Standardize the request with required fields and acceptance criteria.
- Replace informal messages with a visible queue and an owner.
- Automate data transfer when manual copying causes errors.
- Combine related approvals when separate reviews do not reduce risk.
Document the reason for keeping each necessary handoff. A future-state map should show fewer avoidable crossings, clearer ownership, and an explicit response for incomplete work.
Exercise
A support agent sends a complete request to fulfillment. Fulfillment waits six hours before starting, then returns 20% of requests because one field is interpreted differently. What two handoff problems should the map show?
Show answer
It should show a waiting queue between support and fulfillment, and a rework loop from fulfillment back to support caused by the ambiguous field.