Sub topic 1
Who you are managing: vendors, suppliers, and subcontractors
Prerequisites
This chapter assumes you know:
- Basic project vocabulary: scope, schedule, budget, and stakeholders.
- How a work breakdown structure (WBS) organizes project work into parts.
- What a contract is, at a general level.
Vendors, suppliers, and subcontractors
A vendor is any external party you pay for goods or services. Two common kinds are:
- A supplier delivers goods, usually standard items such as cable or software licenses.
- A subcontractor performs a defined piece of project work with its own staff. You remain accountable to your client for that work.
Subcontractors create the most management load because they execute project tasks. Your schedule, quality, and safety risks depend on them.
Deciding what to outsource
Compare the cost of doing work in-house with the cost of buying it. Also weigh skill availability, speed, and control over quality. Outsource work that is well defined and available in the market. Keep work in-house when it is core to the project's value or touches sensitive data.
Writing a scope of work that can be checked
A scope of work lists each deliverable and the test that proves it is done. Write every deliverable in a form you can verify:
- Name the deliverable: "Server room wiring, floors 1 to 3."
- State the acceptance test: "Inspection passed and signed by the project engineer."
If a statement cannot be checked, rewrite it. "High quality work" is not checkable. "Passes inspection with zero open defects" is.
Finding and selecting vendors
Build a shortlist, then score each candidate against weighted criteria. Example:
| Criterion | Weight | Vendor A score (1 to 5) | Weighted score |
|---|---|---|---|
| Relevant experience | 0.40 | 4 | 1.60 |
| Price | 0.35 | 3 | 1.05 |
| Schedule capacity | 0.25 | 5 | 1.25 |
Total the weighted scores for each vendor. Check references before you decide.
Choosing a contract type
The contract type decides who carries the cost risk when work is uncertain.
| Contract type | Who carries cost risk | Best when |
|---|---|---|
| Fixed price | Vendor | Scope is clear and stable |
| Time and materials | Buyer | Scope is uncertain or changing |
| Cost-plus | Buyer | Costs are unknown but must be controlled |
> Hold a fixed price contract only when the scope of work is complete and checkable.
Exercise
Exercise
A vendor must install new network cabling, but the building layout is not yet final. Which contract type fits best, and why?
Show answer
Time and materials, or cost-plus, fits best because the scope is uncertain. The buyer carries the cost risk, so the buyer should set limits and review costs often. A fixed price contract would push the risk onto the vendor, who would then add a large contingency to the price.