Controlling changes to vendor work
This chapter assumes you know the project's scope, schedule, and budget, you can read a work breakdown structure, and a signed contract with the vendor is already in place.
Controlling changes to vendor work
Record every change to vendor scope in a change request (CR) before the vendor starts. The CR states the cost impact, the schedule impact, and who must approve it.
change_request:
id: CR-014
vendor: Northside Electrical Ltd
description: Add two circuits to the server room
cost_impact: 4200
schedule_impact_days: 3
status: submitted
approvals_required:
- project_manager
- sponsor
approved_before_work_starts: trueVerifying invoices and paying against milestones
Pay only for milestones the project has accepted. Subtract the retainage rate, the share of each payment held back until final acceptance.
CONTRACT_VALUE = 120_000
RETAINAGE_RATE = 0.10
milestones = [
{"name": "Design approved", "share": 0.20, "accepted": True},
{"name": "Build complete", "share": 0.50, "accepted": True},
{"name": "Acceptance test passed", "share": 0.30, "accepted": False},
]
earned = sum(CONTRACT_VALUE * m["share"] for m in milestones if m["accepted"])
retainage = earned * RETAINAGE_RATE
payable = earned - retainage
print(f"Earned: {earned:.2f}, retainage held: {retainage:.2f}, payable now: {payable:.2f}")Resolving issues and disputes
Escalate in a fixed order so that each issue has an owner and a deadline.
| Level | Who | When to move up |
|---|---|---|
| 1 | Vendor site lead and your project team | Not resolved within the time limit agreed at kickoff |
| 2 | Project manager and vendor account manager | Not resolved at level 2 within the agreed time |
| 3 | Sponsor and vendor executive | Dispute requires a contract remedy |
If the dispute reaches level 3 without resolution, follow the dispute clause in the contract.
Acceptance, closeout, and lessons learned
Close the contract only when every deliverable has a signed acceptance record, final retainage is released, and all change requests are closed. Hold a lessons-learned review with the vendor, and file the results in the project's lessons log.
Exercise
Exercise
CR-014 adds 4200 to cost and 3 days to the schedule. Under what condition may the vendor start the added work?
Show answer
Only after both the project manager and the sponsor approve the CR, and the CR's approvedbeforework_starts field is true.