Contract terms that matter to the project manager
This chapter assumes you know basic project vocabulary (scope, schedule, budget, stakeholders), how a work breakdown structure is organized, and what a contract is.
Contract terms that matter
Five terms control most of your exposure to a vendor. Check each one before signing:
- Scope and deliverables: what the vendor must produce.
- Acceptance criteria: how you decide a deliverable is done.
- Payment terms: when money moves and how much is held back.
- Change clause: how extra work is requested, priced, and approved.
- Termination clause: how either side can exit, and the required notice.
The contract type sets how much cost risk the vendor carries. A fixed-price contract puts most cost risk on the vendor. Time and materials puts it on you.
Managing vendor risk, insurance, and liability
Request certificates of insurance before work starts. Confirm the liability cap and whether the vendor must repair damage it causes to your site or to other vendors' work. Log each vendor risk in the project risk register with a named owner.
Onboarding and kickoff
Hold a kickoff in the vendor's first week. Invite the vendor's lead, your sponsor, and each internal team that will work with the vendor. Cover:
- Scope and acceptance criteria
- Named contacts on both sides
- Site access and safety rules
- The escalation path
Send written minutes within 24 hours.
Setting a communication and reporting rhythm
Agree on a fixed cadence before work begins: a weekly status report, a standing working call, and a monthly review with your sponsor. Name one contact on each side for each channel so that requests do not get lost.
Fitting vendor work into the project schedule
Enter every vendor deliverable into the master schedule as a task with a defined predecessor and successor. Track the vendor's float separately from your own. When a vendor slips, trace which downstream tasks move.
| Contract type | Cost risk carried mainly by | Best when |
|---|---|---|
| Fixed price | Vendor | Scope is well defined |
| Time and materials | Buyer | Scope is uncertain |
| Cost-plus | Buyer | Work is exploratory and cost must be tracked |
Monitoring performance and holding reviews
Compare planned and actual progress every week against the agreed acceptance criteria, not the vendor's own status summary. Hold a formal review at each milestone and record the outcome.
Exercise
A vendor asks to start extra work based on a verbal request from a site engineer. What should you do first?
Show answer
Stop the extra work until the change request is submitted in writing and approved by the people the contract names, usually the project manager and sponsor. Then record the cost and schedule impact before work resumes.