Sub topic 4
Escalation of commitment: how small extensions become long detours
This chapter assumes you have worked on a project for several weeks or more and have set goals or milestones before. It builds on the previous chapter on sunk costs. Reading short Python is helpful for one example, but not required.
What escalation of commitment is
Escalation of commitment is the pattern of putting more time, money, or effort into a course of action after evidence suggests it is not working. Each new investment is justified by the earlier ones.
It is related to the sunk cost fallacy, but it is not the same thing. Sunk cost is a single mistaken piece of reasoning: "I have already spent so much." Escalation is the process that reasoning produces over time. A sequence of decisions, each of which looks small, adds up to a large commitment that nobody chose in one step.
The key point for this chapter is that escalation rarely feels like escalation. No one decides "I will spend six months on a failing idea." They decide "one more week," and then they decide it again.
How small extensions become long detours
Consider a person building a budgeting app in their spare time. They planned four weeks.
- Week 4: the app is not ready. "Two more weeks will finish it."
- Week 6: the main feature works, but nobody has tried it. "I will add a second feature first, so the launch is stronger."
- Week 9: three testers try it, and two stop using it after a day. "The design is the problem. A redesign will fix it."
- Week 13: the redesign is done. Retention is still low. "The first users were not the right audience."
- Week 17: the person is now four times past the original plan, and each earlier step still seems reasonable when viewed alone.
Every step above has a plausible story attached. That is what makes escalation hard to catch. The stories are not lies. Some are even partly true. The problem is that the story changes each time while the outcome, low use, stays the same.
The loop on the left side (B to C to D to E and back to B) continues indefinitely unless something outside it intervenes. The path to F is the intervention, and it works only if it was set up in advance. Later chapters cover kill criteria and checkpoints in detail. Here, the goal is to recognize the loop.
Why it happens
Several forces push in the same direction. Knowing them helps you spot which one is active in a given case.
- Sunk cost reasoning. Past investment feels like something that will be wasted if you stop. Stopping makes the loss real.
- Loss aversion. People feel a loss more strongly than an equal gain. Abandoning an idea locks in a loss. Continuing keeps the possibility of recovery open, even if it is unlikely.
- Self-justification. If you chose this idea, stopping suggests the choice was wrong. Continuing protects your view of yourself as a good decision maker.
- Hidden progress. Effort produces visible output: code, pages, prototypes. You can see that "something exists." This is easy to confuse with evidence that the idea works.
- Social commitment. You told your team, your manager, or your friends. Reversing course has a social cost that rises with each public statement.
- Moving goalposts. The success definition shifts so that the current state looks like progress. "Launch" becomes "beta," then "soft launch," then "learning phase."
Research on escalation, going back to studies by Barry Staw in the 1970s, found a notable detail. People escalate more when they feel personally responsible for the original decision. Someone who inherits a failing project tends to cut it more readily than the person who started it. This is useful in practice: a fresh view often decides better.
Signs that you are escalating
You cannot see your own escalation easily, so it helps to have a checklist of observable signs.
| Sign | What it looks like | Question to ask |
|---|---|---|
| Repeated extensions | The deadline has moved two or more times | Would I approve this extension if it were the first request? |
| Changing justification | Each delay has a different reason | What has the outcome measure actually done? |
| Rising spend, flat results | Effort goes up, key numbers do not | What did the last extension buy? |
| Narrowing success | The goal is smaller than the original goal | Would the original goal have justified starting? |
| Avoiding the test | You add features instead of showing it to users | What is the cheapest test of the core claim, and why have I not run it? |
| Defensive reaction | You feel irritated when someone asks "is this working?" | Why does the question feel threatening? |
Two of these deserve extra attention.
The first is the fresh-start test. Ask: "If I had not started this idea, and I knew everything I know now, would I begin it today with the remaining cost?" If the honest answer is no, you are probably escalating. The past spending does not appear in this question at all, which is the point.
The second is narrowing success. A project that began as "a tool 500 people pay for" and becomes "a tool I personally find useful" has not succeeded. It has been redefined. A redefinition can be legitimate, but it should be a deliberate decision made in the open, not something that happens quietly.
Hard but promising versus escalating
Persistence is not the enemy. A hard idea that is making real progress should continue. The difference is in the evidence trend, not in the difficulty.
| Row | Hard but promising | Escalating |
|---|---|---|
| Difficulty | High | High |
| Key measures over time | Improving, even if slowly | Flat or falling |
| Reasons for delay | Specific and testable, and fixed when addressed | Vague, or a new one each time |
| What you learn each cycle | Something that changes the next step | Little that changes the plan |
| Success definition | Unchanged | Quietly lowered |
| Response to outside feedback | Used | Explained away |
A useful rule is that a delay is acceptable when it comes with a prediction. "If I fix the onboarding flow, I expect sign-ups to complete at 40% instead of 15%." If you run the fix and the number does not move, you have learned something real. If you cannot state what number should change, the extension is not a test. It is only more time.
Putting a number on the extension
You can make escalation visible by tracking how far you are from the original plan. The following Python program computes an overrun ratio and flags extensions that have no stated prediction.
from dataclasses import dataclass
@dataclass
class Extension:
weeks_added: float
reason: str
prediction: str # empty string means no testable prediction
def escalation_report(planned_weeks, extensions):
added = sum(e.weeks_added for e in extensions)
overrun = added / planned_weeks
untested = [e.reason for e in extensions if not e.prediction.strip()]
warnings = []
if len(extensions) >= 2:
warnings.append("two or more extensions")
if overrun >= 0.5:
warnings.append(f"overrun is {overrun:.0%} of the original plan")
if untested:
warnings.append(f"{len(untested)} extension(s) had no testable prediction")
return warnings
extensions = [
Extension(2, "finish main feature", ""),
Extension(3, "add second feature", ""),
Extension(4, "redesign interface", "week-1 retention rises from 10% to 30%"),
Extension(4, "find better audience", ""),
]
for w in escalation_report(4, extensions):
print("WARNING:", w)Running it prints three warnings: two or more extensions, an overrun of 325% of the original plan, and three extensions without a testable prediction. The thresholds (two extensions, 50% overrun) are examples. Choose your own and write them down before the project starts, since a threshold chosen midway is easy to adjust to fit what you want to do.
Countermeasures you can use now
You do not need the full kill-criteria system to start reducing escalation. These habits help immediately.
- Cap extensions in advance. Decide at the start how many extensions are allowed and how long each may be. A common rule is one extension of at most 25% of the original timebox.
- Require a prediction with each extension. Write one sentence stating what will change and by how much.
- Make the extension request a separate event. Do not extend in the middle of a work session when you are tired and attached. Schedule a short review, and write the decision down.
- Ask an outsider. Describe the facts, not your story, to someone with no stake. Ask what they would do.
- Run the fresh-start test at every extension.
- Change who decides. If you can, have someone who did not choose the idea make the call.
Edge cases and common errors
- Treating all extensions as bad. Some tasks are legitimately underestimated. An extension with a clear cause, a prediction, and a cap is a normal planning adjustment. Escalation is about extensions that lack these.
- Overcorrecting. People who learn about escalation sometimes quit at the first setback. A single missed milestone is not proof of failure. Compare the trend across several checkpoints.
- Escalating in small, unrecorded steps. Many extensions are never written down, so the total is invisible. Keep a running count of time and money spent against the plan.
- Group escalation. In teams, each member may assume others have checked the evidence. Name one person responsible for asking the stop question at each review.
- Irreversible commitments. Escalation is more dangerous when each step also reduces your options: signing contracts, hiring, or making public promises. Check how reversible each extension is before agreeing to it.
Exercise
A freelancer planned a six-week project to build a client reporting tool. At week 6 it was not done, so she extended by two weeks. At week 8 she extended by three more weeks to "polish it." At week 11 she extended again to "add features customers have asked for," although no customer has used the tool yet. Identify two signs of escalation of commitment in this story, and describe one change she could make at the next decision point.
Show answer
Signs include repeated extensions (three so far, now 5 weeks added to a 6-week plan, which is an 83% overrun), changing justifications each time (finish, polish, add features), and avoiding the test (adding features before any customer has used it). Any two of these are correct. A good change is to stop extending without a prediction and instead run the cheapest test of the core claim: give the tool to one or two real customers and measure whether they use it. She could also apply the fresh-start test, or ask an outsider, or set a cap on further extensions.
Exercise
Using the Python function above, would an idea with a 10-week plan and two extensions of 1 week each, both with written predictions, produce any warnings? Explain which rule triggers.
Show answer
Yes, one warning. There are two extensions, so "two or more extensions" triggers. The overrun is 2 / 10 = 20%, below the 50% threshold, and both extensions have predictions, so those rules do not trigger. The single warning is a prompt to review, not a verdict to stop.