Sub topic 3
Implementing Approved Changes and Updating Baselines
This chapter assumes you know the basic terms scope, schedule, cost, quality, and risk, and that you have read a project management plan. It also assumes the Change Control Board has already approved a change request.
Implementing approved changes and updating baselines
A baseline is an approved version of a plan, such as the scope, schedule, or cost baseline. Project work is measured against baselines. After an approved change is built, the team verifies it and then updates the affected baselines.
baselines = {"scope": "v1.0", "schedule": "v1.0", "cost": 120000}
change = {
"id": "CR-014",
"areas_affected": ["schedule", "cost"],
"new_values": {"schedule": "v1.1", "cost": 138000},
}
def apply_change(baselines, change):
updated = dict(baselines)
for area in change["areas_affected"]:
updated[area] = change["new_values"][area]
return updated
print(apply_change(baselines, change))Emergency changes and after-the-fact review
An emergency change is a fix that cannot wait for a Board meeting, such as a security patch during an outage. The change management plan should state who may approve these changes. The team logs the change and submits it to the Board afterwards. If the Board rejects it, the team must roll it back.
Configuration management and change control
Configuration management tracks the versions of deliverables and documents. Change control decides whether a change happens. Each approved change should name the configuration items it modifies, so the team can see which versions are affected.
Handling change in agile and hybrid projects
Agile teams keep a single backlog of requested changes and let the product owner set priority. Changes that affect budget or release date still need Board or sponsor approval. In hybrid projects, use the backlog for work packages and keep formal approval for baseline changes.
Pitfalls: scope creep, informal approvals and stale baselines
- Scope creep: small unlogged additions build up until the schedule fails.
- Informal approvals: a verbal yes has no record and may lack authority.
- Stale baselines: old values stay in the plan, so every later report is wrong.
Exercise
An approved change adds two weeks to the schedule. Which baseline must you update, and when?
Show answer
Update the schedule baseline after the change is implemented and verified, and record the new end date in the change log.