Baselines: what a change is measured against
Prerequisites
You should know the five project performance areas (scope, schedule, cost, quality, and risk), and you should have seen a project management plan with its subsidiary plans. You should also know the roles of sponsor, project manager, and stakeholder.
Why baselines matter
A baseline is an approved reference version of a project measure. The three standard baselines are the scope baseline, the schedule baseline, and the cost baseline. Together they form part of the project management plan. A change is only meaningful when you can compare it against a baseline, so every change request should state which baseline it moves and by how much.
What integrated change control does and why
Integrated change control is the process that reviews every requested change to a baseline or deliverable. It decides whether the change proceeds, then keeps the plan, baselines, and documents consistent afterwards. Without it, teams accept small changes informally, and the baseline drifts away from what the project is actually doing.
Writing and classifying change requests
A change request names the requester, the reason, the type, and the baselines it affects. Common types are corrective action, preventive action, defect repair, and update. Classifying the request early tells the reviewers how urgently it needs attention and which controls apply.
The change management plan: rules set in advance
The change management plan defines how changes are handled before any request arrives. It sets the review path, the decision authority, the impact thresholds that trigger a full review, and the required records. Writing these rules in advance keeps decisions consistent under pressure.
Measure a proposed change against the baseline before you decide. The following code compares a proposal with the approved baseline.
baseline = {"scope_items": 40, "schedule_weeks": 26, "cost": 180000}
proposed = {"scope_items": 42, "schedule_weeks": 29, "cost": 198000}
for key, approved in baseline.items():
change = proposed[key] - approved
pct = change / approved * 100
print(f"{key}: {change:+} ({pct:+.1f}%)")Running this prints scope_items: +2 (+5.0%), schedule_weeks: +3 (+11.5%), and cost: +18000 (+10.0%).
> The baseline is the reference point, not the current plan. Once an approved change updates the baseline, the new values become the reference.
Exercise
A project has a schedule baseline of 26 weeks. A change request proposes 29 weeks. Which baseline does the change request compare against, and what percentage increase does it represent?
Show answer
It compares against the approved schedule baseline of 26 weeks. The increase is 3 weeks, or 3 / 26 × 100 ≈ 11.5%.