Sub topic 2
Assessing the impact of a change
This chapter assumes you know the five project areas (scope, schedule, cost, quality, and risk), can read a project baseline, and understand the roles of sponsor and project manager.
Measuring impact against the baseline
Every change is judged against the approved baseline. The baseline is the agreed scope, schedule, and cost plan. For each change request, estimate how far it moves each area from that baseline. Record the estimate in the request itself, not in a side conversation.
Assess each area separately:
- Scope: which deliverables, features, or tests are added, removed, or altered?
- Schedule: how many days does the critical path move?
- Cost: what is the one-off and ongoing cost change?
- Quality: does the change affect acceptance criteria or test coverage?
- Risk: does it add new risks, or raise the likelihood or effect of existing ones?
- Resources: does it need people, skills, or equipment not already planned?
Turning impact into a routing decision
The change management plan sets thresholds in advance. A simple rule scores each area from 1 (low) to 3 (high) and routes the request by its total or its worst area:
impacts = {
"scope": 2,
"schedule": 3,
"cost": 2,
"quality": 1,
"risk": 3,
"resources": 1,
}
def assess(impacts: dict[str, int]) -> str:
total = sum(impacts.values())
worst = max(impacts, key=impacts.get)
if impacts[worst] >= 3 or total >= 10:
return f"Escalate to the Change Control Board; highest impact is {worst}"
return "Project manager may decide within delegated authority"
print(assess(impacts))Running this prints Escalate to the Change Control Board; highest impact is schedule.
> Note: the threshold must be written in the change management plan before the request arrives. A threshold set after a request is on the table invites bias.
Common errors
- Judging only cost. A change that adds no money can still push the schedule past a contract date.
- Ignoring knock-on effects. A scope change often adds risk and resource needs that the original request did not mention.
- Estimating without the people who will do the work.
Exercise
Exercise
A change adds two features (scope 2), delays the critical path by one week (schedule 2), and adds no cost, quality, risk, or resource impact (each 1). Using the total-or-worst rule above, who decides?
Show answer
The total is 2 + 2 + 1 + 1 + 1 + 1 = 8, and the worst area scores 2. Neither reaches the escalation threshold (a score of 3 or a total of 10), so the project manager decides within delegated authority.