Sub topic 12
Three ways to get to S/4HANA
This chapter assumes you know the ECC 6.0 baseline and the main S/4HANA data model changes from earlier chapters: SAP HANA as the database, the Universal Journal, Business Partner, and MATDOC. It also assumes you have seen the term "custom code" in an ABAP context. The chapter explains the three standard routes from ECC to S/4HANA, what each one does to your data and configuration, and the errors teams most often make when choosing.
The three approaches at a glance
SAP describes three transition paths. The names in common use differ from SAP's official ones, so you will see both.
| Approach | Common nickname | What happens | What you keep |
|---|---|---|---|
| New implementation | Greenfield | Install a fresh S/4HANA system, configure it, and load selected data | Chosen master data and open items, not the old system's configuration or custom code |
| System conversion | Brownfield | Convert the existing ECC system in place, in one technical project | Configuration, custom code, and the full data history |
| Selective data transition | Mix and match, shell conversion | Build a new system or copy a shell of the old one, then move chosen data, such as certain company codes or a time slice | A negotiated subset, depending on the scenario |
None of the three is "best." Each trades speed, risk, and cleanup effort differently.
New implementation
In a new implementation you set up a new S/4HANA system from scratch. You do not carry the ECC configuration over. You define the organizational structure, chart of accounts, and processes again, usually adopting SAP's standard best practices where you can.
You then bring data across with migration tools. The usual tool is the SAP S/4HANA Migration Cockpit, which loads business objects such as Business Partners, materials, open purchase orders, and GL balances. You choose what to load. Many teams load master data, open items, and balances, and leave closed transactions behind in an archive or the old system.
Advantages:
- You drop years of configuration that no one fully understands.
- Custom code does not come along unless you decide it should. This forces a review of whether each custom object is still needed.
- Process redesign is natural, because you are already reconfiguring everything.
Costs:
- It is the largest change-management effort of the three. Every process is re-specified, re-tested, and re-trained.
- Historical data is not automatically available in the new system. You must decide how to keep it reachable for audits.
- Integration with surrounding systems must be re-established, not just adjusted.
System conversion
A system conversion changes the existing ECC system into an S/4HANA system. The technical tool is the Software Update Manager (SUM). If the source database is not SAP HANA, SUM can combine the software update and the database move in one run using the Database Migration Option (DMO). The result is the same system ID, configuration, custom code, and data, now running on S/4HANA with the new data model.
The conversion is more than a technical upgrade. SUM runs data conversions that reshape tables. Financial data moves into the Universal Journal, material documents move into MATDOC, and customers and vendors must exist as Business Partners. The mandatory preparation therefore happens before the technical run, not during it.
Preparation includes:
- Checking the source system against the conversion prerequisites, such as Unicode and a supported start release.
- Working through the Simplification Item Catalog and confirming which items apply to you. A later chapter covers the readiness tools.
- Generating the stack file with the Maintenance Planner.
- Synchronizing customers and vendors with Business Partners (see the next section).
- Adapting custom code and cleaning up data in the source system.
Advantages:
- Your existing configuration, historical data, and many processes continue unchanged.
- It is generally the shortest path in elapsed time for a company that is happy with its current processes.
Costs:
- You inherit whatever is wrong in the source system, including dirty data and unused customizing.
- Downtime for the production cutover is a real constraint. Teams size it with test runs and can reduce it with SAP's downtime-optimized techniques.
- The conversion is mostly one-way. You normally restore from backup to go back, so rehearsals on copies of production are essential.
Business Partner as a conversion gate
A common blocker is Business Partner. S/4HANA expects the Business Partner to be the single master record for customers and vendors. In ECC, you prepare for this with Customer/Vendor Integration (CVI), which links the old customer and vendor records to Business Partners. Conversion cannot proceed cleanly if records have no link.
The following report counts customers that have no Business Partner link in an ECC system where CVI tables exist. Run it in a test system first.
REPORT z_check_cvi_customers.
SELECT COUNT( * )
FROM kna1
LEFT OUTER JOIN cvi_cust_link
ON cvi_cust_link~customer = kna1~kunnr
WHERE cvi_cust_link~customer IS NULL
INTO @DATA(lv_unlinked).
WRITE: / |Customers without a Business Partner link: { lv_unlinked }|.A result above zero means the synchronization step is not finished. The same check applies to vendors, using lfa1 and cvi_vend_link. This report is a quick sanity check, not a replacement for SAP's own pre-conversion checks.
Selective data transition
Selective data transition covers scenarios where neither full path fits. It starts from the idea that you move a chosen part of your landscape and its data, not everything. Typical situations:
- Company code carve-out or merge. You move only some legal entities to a new S/4HANA system.
- Consolidating several ECC systems. You bring multiple sources into one S/4HANA system.
- Keeping history but redesigning. You want a new configuration, such as a new chart of accounts, and also want a selected time slice of historical data.
- Staged landscape change. You convert a copy of the system as a "shell" with configuration but without transactional data, then load the data you choose.
Selective data transition is usually delivered with SAP services and tooling for data transformation, for example SAP Landscape Transformation, and with specialist partners. It is the most variable path. The project is only as predictable as your data selection rules.
Advantages:
- It can fit complex structures that the other two cannot.
- You can keep a defined amount of history while redesigning.
Costs:
- Data consistency is your responsibility. Moving a subset of finance data while leaving related logistics data behind can break reconciliation.
- It needs tooling and skills beyond a standard conversion.
- Planning effort is high, because the data scope rules must be defined and tested up front.
How they differ in practice
The table below compares the paths on the factors that decide most projects.
| Factor | New implementation | System conversion | Selective data transition |
|---|---|---|---|
| Configuration reuse | None by default | Full | Depends on scenario |
| Historical data | Only what you load | All | Chosen subset |
| Custom code | Rebuilt as needed | Adapted | Adapted as needed |
| Process redesign | Easy | Constrained | Possible |
| Technical risk | Lower for the system, higher for data loading | Higher for cutover | Highest, from data selection |
| Business change | Largest | Smaller | Varies |
Choosing between them
The next chapters cover the final decision and roadmap in detail. The questions below show how the three paths relate.
The flow is a starting point and not a rule. Several factors can override it.
- Code volume. Large amounts of custom code that is still valuable favor conversion.
- Data quality. Poor data or years of unused customizing favors a new implementation or a selective approach.
- Downtime tolerance. A tight cutover window pushes you toward careful conversion rehearsal, or toward a path that builds the new system in parallel.
- Timeline. The maintenance deadlines discussed earlier put a ceiling on how long any path may take.
Common errors
- Treating conversion as a technical upgrade. The data model changes affect finance, logistics, and master data owners, not only the Basis team.
- Choosing greenfield to avoid cleanup, then recreating the same complexity. Without a firm design authority, the new system drifts back toward the old one.
- Skipping Business Partner and CVI preparation until late in the project.
- Underestimating the number of test cycles. Plan multiple conversion rehearsals on realistic copies of production.
- Mixing approaches by accident. A "conversion with some redesign" is common and valid, but you should decide it deliberately.
Summary
A new implementation gives a clean start and the most change. A system conversion keeps what you have, at the cost of inheriting it. A selective data transition fits special structures and carries the highest planning effort. In every case, start from your actual constraints: process goals, data quality, custom code, downtime, and the maintenance timeline.
Exercise
A company runs ECC 6.0 with stable processes, a large body of custom ABAP code that is still in daily use, and a requirement to keep all ten years of financial history in the same system. It has no plans to merge or split legal entities. Which approach fits best, and which preparation step involving customers and vendors must be finished first?
Show answer
System conversion fits best. Existing configuration, custom code, and full history are kept, and no structural change calls for selective data transition. Before the conversion, customers and vendors must be synchronized with Business Partners through Customer/Vendor Integration, so every record has a link.
Exercise
Name two risks that apply to a selective data transition and not as strongly to a system conversion.
Show answer
Data consistency across modules, because moving only a subset of data can break reconciliation between finance and logistics. Also the need for extra tooling and specialist skills, because the project depends on defined and tested data selection rules.