Sub topic 15
Choosing an approach and building a roadmap
This chapter assumes you know the three paths to S/4HANA (new implementation, system conversion, selective data transition). It also assumes you know the readiness tools (Simplification Item Catalog, Readiness Check, Maintenance Planner) and the main data model changes (Universal Journal, Business Partner, MATDOC). Here you combine that knowledge into a decision and a plan.
Start from constraints, not preferences
Teams often pick an approach by habit. A better method is to list the constraints that cannot move, then see which approaches survive.
Four groups of constraints decide most cases:
- Time. The ECC maintenance deadline, contract end dates, and any merger or divestiture date.
- Process. How much of your current process you want to keep, and how much you are willing to redesign.
- Data. How much history must stay in the live system, and how clean the master data is.
- Capacity. Whether your team can run a large change program next to normal operations.
The three approaches compared on decision criteria
| Criterion | New implementation | System conversion | Selective data transition |
|---|---|---|---|
| Starting point | Clean new system | Your existing ECC system, converted in place | New or converted system, with data picked from one or more sources |
| Process redesign | High. Fresh design is the point | Low to medium. Existing processes carry over | Medium to high. You choose per scope |
| Custom code | Rebuilt or dropped by choice | Must be analyzed and adapted | Handled per scope |
| Historical data | Only what you load | All history stays | You define what moves |
| Downtime | Cutover from old to new system | One technical downtime window | Depends on tooling and scope |
| Typical fit | Heavy customization to retire, or a move to a standardized process | Fast move that keeps current process | Carve-outs, mergers, consolidation of several ECC systems |
| Main risk | Longer design effort and data migration work | Carrying old problems into the new system | Complex scoping and a dependence on specialist tooling |
Treat this table as a starting point. The real cost depends on your landscape, so confirm the estimates in a technical assessment.
A decision flow
The flow below asks the questions in the order that usually eliminates options fastest.
The last branch matters. If the Readiness Check shows many blocking simplification items or a large amount of unusable custom code, a conversion may cost more than it first appeared. In that case a new implementation or a staged cleanup can be cheaper.
Use readiness results as evidence
Run the tools early and use their output as inputs to the decision:
- Simplification Item Catalog and Readiness Check. Count the items that apply to you, and note which ones need action before conversion, such as converting customers and vendors to Business Partner.
- Custom code analysis. Estimate how many objects need changes. Code that reads removed aggregate tables, or that touches MKPF/MSEG directly, will need work. Code that reads ACDOCA or MATDOC through compatibility views often keeps working, but you must test it.
- Maintenance Planner. Check that your add-ons and connected systems have S/4HANA-compatible versions.
Record the results as numbers in your assessment, for example "412 custom objects need adaptation" rather than "a lot of custom code".
Anchor the timeline to the maintenance deadlines
Work backward from the deadline. SAP's published position at the time of writing is that mainstream maintenance for SAP Business Suite 7 core application releases, including ECC 6.0, ends at the end of 2027, with optional extended maintenance available beyond that. SAP has also published additional options tied to its cloud offerings. These terms can change, so verify them in SAP Note 1648480 and in SAP's current maintenance statements on the SAP Support Portal before you commit a date to a plan.
Backward planning works like this:
- Fix the date by which you must be live, and subtract a buffer, because extended maintenance is usually priced higher.
- Subtract the cutover and hypercare period.
- Subtract the test cycles. Plan at least a technical test, an integration test, and user acceptance.
- Subtract realization: adapting code, converting data, building Fiori roles.
- What remains is the time available for assessment and design. If it is negative, you need a different approach or a different support option.
A simple weighted scoring script
A scoring sheet makes trade-offs visible to stakeholders. The script below takes your own weights and ratings, so the output reflects your judgment and not a fixed truth.
weights = {"speed": 3, "process_change": 2, "history": 2, "code_effort": 3}
# Ratings from 1 (poor) to 5 (strong) for each approach, set by your team.
ratings = {
"new_implementation": {"speed": 2, "process_change": 5, "history": 2, "code_effort": 4},
"system_conversion": {"speed": 5, "process_change": 2, "history": 5, "code_effort": 2},
"selective_transition": {"speed": 3, "process_change": 4, "history": 4, "code_effort": 3},
}
def score(rating):
return sum(weights[k] * rating[k] for k in weights)
for name, rating in sorted(ratings.items(), key=lambda item: -score(item[1])):
print(f"{name}: {score(rating)}")Change the weights and see whether the ranking flips. If a small change flips it, the decision is close, and you should decide on risk and capacity rather than on the score.
Phases of a roadmap
A roadmap names phases, owners, and exit criteria. A typical one for a conversion looks like this:
| Phase | Main activities | Exit criterion |
|---|---|---|
| Assess | Readiness Check, custom code analysis, license and deployment review | Approved scope and approach |
| Prepare | Clean master data, start Business Partner conversion, remove unused custom code, plan add-on upgrades | Blocking items resolved |
| Convert and build | Sandbox conversion, code adaptation, Fiori roles, interface changes | Working development system |
| Test | Technical, integration, performance, and acceptance tests, plus at least one full dress rehearsal of cutover | Signed-off test results |
| Cutover | Final conversion within the downtime window, data checks | Go-live decision met |
| Hypercare | Defect fixing, performance tuning, user support | Stable operation |
For a new implementation, replace "Convert and build" with design workshops and data migration builds, and expect a longer "Prepare" phase for data cleanup.
Deployment option and its effect on the plan
Deployment choice changes both the roadmap and the later upgrade rhythm:
- On premise gives the most control over custom code and timing, and leaves infrastructure and upgrades to you.
- Private cloud keeps wide customization while shifting infrastructure operation to a provider.
- Public cloud enforces standard processes and a regular update cadence, which usually points toward a new implementation and limits custom code.
If your answer to "how much of our custom code must survive" is "most of it," public cloud is rarely the right fit.
Common mistakes
- Choosing the tool before the scope. The approach follows from scope and constraints, not from a vendor's favored path.
- Treating conversion as a purely technical project. Finance, logistics, and master data owners must test their processes, because the Universal Journal, Business Partner, and MATDOC changes affect reports and interfaces.
- Ignoring data volume. Large history increases conversion runtime and the size of the downtime window. Archive what you can before you start.
- Skipping rehearsals. The first full-size conversion run almost always finds problems. Run it more than once before production.
- Planning to the deadline day. A plan that ends on the last day of maintenance has no slack for a failed cutover.
Putting it together
A finished roadmap answers six questions: what scope moves, which approach, which deployment option, what the deadline is and where it was verified, which risks are open, and who owns each phase. If you can answer all six with evidence from the readiness tools, you have a plan you can defend.
Exercise
A company runs one ECC 6.0 system, has lightly modified processes, and wants to keep ten years of financial history. Its readiness check shows moderate custom code impact, and its go-live must come well before the ECC mainstream maintenance end date. Which approach fits best, and which question would change your answer?
Show answer
System conversion fits best. It keeps existing processes and all history, and it is usually the fastest route for a single, reasonably clean system. The answer would change if the company decided to redesign its processes or retire most of its custom code, which favors a new implementation, or if only part of the business were moving or several systems were being merged, which favors selective data transition. A readiness result showing many blocking items or a large custom code backlog would also justify rechecking the choice.
Exercise
Work backward from a go-live deadline and list the five time blocks you subtract, in order, to find how much time remains for assessment and design. Where should you verify the ECC deadline itself?
Show answer
Subtract a safety buffer, then cutover and hypercare, then testing, then realization (code adaptation, data conversion, Fiori roles). What remains is the time for assessment and design. Verify the ECC maintenance dates in SAP Note 1648480 and in SAP's current maintenance statements on the SAP Support Portal, and record the date you checked.