Sub topic 1
The inputs: BAC, PV, EV, and AC
Earned value management (EVM) is a method for checking project progress against the plan using money and work measured in the same units. This chapter defines the four inputs every EVM forecast needs and shows how to turn them into performance indicators and a forecast for the one-off overrun case.
Prerequisites
You should know basic project vocabulary, including scope, budget, and schedule. You should also understand what a baseline is, and be comfortable with ratios and simple arithmetic.
The four inputs
- BAC (Budget at Completion): the total approved budget for the project.
- PV (Planned Value): the budgeted cost of the work scheduled to be done by today.
- EV (Earned Value): the budgeted cost of the work actually completed by today.
- AC (Actual Cost): the real cost incurred to complete that work by today.
Reading performance: CV, SV, CPI, and SPI
Two variances show the gap between plan and reality. Cost variance (CV) is EV minus AC. Schedule variance (SV) is EV minus PV. Indices show the same gaps as ratios: CPI is EV divided by AC, and SPI is EV divided by PV. A value below 1 means the project is over cost or behind schedule.
| Measure | Formula | Below 1 or negative means |
|---|---|---|
| CV | EV - AC | Over budget |
| SV | EV - PV | Behind schedule |
| CPI | EV / AC | Spending more than the work is worth |
| SPI | EV / PV | Progressing slower than planned |
bac, pv, ev, ac = 100000, 50000, 40000, 48000
cv = ev - ac
sv = ev - pv
cpi = ev / ac
spi = ev / pv
print(cv, sv, round(cpi, 4), round(spi, 4))Output: -8000 -10000 0.8333 0.8
> The script above is plain Python with no dependencies, so it runs as shown.
What EAC and ETC are, and how they fit together
EAC (Estimate at Completion) is the forecast of the total cost of the project. ETC (Estimate to Complete) is the forecast of the cost still to come. The two always add up to a known number: ETC equals EAC minus AC. Choosing an EAC method therefore also sets the ETC.
EAC when the overrun was a one-off
If the overrun came from a single event, such as a delayed delivery, the rest of the work should cost what it was planned to cost. The formula is EAC = AC + (BAC - EV). In the example, EAC = 48000 + (100000 - 40000) = 108000, so ETC = 60000.
Exercise
BAC is 60000, EV is 30000, and AC is 25000. What is the one-off EAC?
Show answer
EAC = 25000 + (60000 - 30000) = 55000.