Sub topic 3
EAC when cost and schedule both drive the outcome
This chapter assumes you know BAC (budget at completion), PV (planned value), EV (earned value), and AC (actual cost). You should also be able to compute CPI (cost performance index, EV divided by AC) and SPI (schedule performance index, EV divided by PV).
EAC when cost and schedule both drive the outcome
Use this formula when schedule slippage also raises cost, such as when delays keep staff on the payroll longer:
EAC = AC + (BAC - EV) / (CPI x SPI)
With BAC 100000, PV 50000, EV 40000, and AC 48000, CPI is 0.8333 and SPI is 0.8. The forecast is EAC = 48000 + 60000 / 0.6667 = 138000.
Bottom-up EAC: re-estimating the remaining work
When the team can rebuild the estimate for the remaining work, add that new estimate to actual cost:
EAC = AC + bottom-up ETC
If the team estimates 85000 for the work left, EAC = 48000 + 85000 = 133000.
TCPI: the efficiency the remaining work demands
TCPI (to-complete performance index) is the cost efficiency the remaining work must reach to hit a target.
- Against BAC: (BAC - EV) / (BAC - AC) = 60000 / 52000 = 1.1538. A value above 1 means the team must beat its current efficiency to stay on budget.
- Against EAC: (BAC - EV) / (EAC - AC) = 60000 / 90000 = 0.6667. A value below 1 means the revised forecast asks for less efficiency than the team has shown so far.
def forecast(bac, pv, ev, ac, bottom_up_etc=None):
cpi = ev / ac
spi = ev / pv
results = {
"EAC (cost and schedule)": ac + (bac - ev) / (cpi * spi),
"TCPI to BAC": (bac - ev) / (bac - ac),
}
if bottom_up_etc is not None:
results["EAC (bottom-up)"] = ac + bottom_up_etc
return results
for name, value in forecast(100000, 50000, 40000, 48000, 85000).items():
print(f"{name}: {value:.4f}")Choosing and justifying a method
| Method | Use when | Formula |
|---|---|---|
| Atypical | The past overrun was a one-off | AC + (BAC - EV) |
| Typical | Current cost efficiency will continue | BAC / CPI |
| Cost and schedule | Schedule slippage raises cost | AC + (BAC - EV) / (CPI x SPI) |
| Bottom-up | The team can re-estimate the remaining work | AC + new ETC |
Justify the choice by naming the cause of past variance and the evidence for it. Show the other methods' results next to the chosen one.
Pitfalls and how to report a forecast
- CPI x SPI is a rule of thumb, not a law. Check it against the project's history before relying on it.
- Do not mix units, and note any unapproved changes included in AC.
- Report EAC as a range, with the method, the data date, and the key assumptions.
Exercise
With BAC 100000, EV 40000, and AC 48000, what is the atypical EAC?
Show answer
108000, because AC + (BAC - EV) = 48000 + 60000.