Sub topic 2
EAC When Current Cost Performance Will Continue
This chapter assumes you know BAC (Budget at Completion), PV (Planned Value), EV (Earned Value), and AC (Actual Cost). You should also be able to compute CPI (Cost Performance Index) as EV / AC.
The typical EAC formula
Estimate at Completion (EAC) is the forecast of the project's total final cost. When the cost efficiency seen so far will continue for the rest of the work, use:
EAC = BAC / CPI
Use this formula when the team's past cost performance reflects a steady pattern rather than a one-time event.
Take a project with BAC = 100000, PV = 50000, EV = 40000, and AC = 48000. CPI is 40000 / 48000, about 0.8333. The forecast is 100000 / 0.8333, which is 120000.
bac, pv, ev, ac = 100000, 50000, 40000, 48000
cpi = ev / ac
eac = bac / cpi
print(round(eac)) # 120000From EAC to ETC
Estimate to Complete (ETC) is the money still needed to finish the work. It is the forecast total minus what has already been spent:
ETC = EAC - AC
For this project, ETC = 120000 - 48000 = 72000. The team has spent 48000 and needs to spend 72000 more.
| Measure | Meaning | Value |
|---|---|---|
| EAC | Forecast total cost | 120000 |
| AC | Spent so far | 48000 |
| ETC | Still to spend | 72000 |
Variance at Completion: the forecast gap to budget
Variance at Completion (VAC) shows how far the forecast total differs from the budget:
VAC = BAC - EAC
Here, VAC = 100000 - 120000 = -20000. A negative value means the project is forecast to overrun its budget by 20000.
Exercise
BAC is 100000, EV is 40000, and AC is 48000. What are the typical EAC, ETC, and VAC?
Show answer
CPI = 40000 / 48000 = 0.8333. EAC = 100000 / 0.8333 = 120000. ETC = 120000 - 48000 = 72000. VAC = 100000 - 120000 = -20000.