The default rule: promises must be performed
Prerequisites
This chapter assumes you know the basic elements of a contract (offer, acceptance, consideration), the difference between express and implied terms, and what breach and damages mean.
Strict performance
Under English contract law, a promise binds the person who makes it. If a supplier agrees to deliver goods by 1 March, it must deliver by 1 March. Courts generally do not excuse late or failed performance just because circumstances changed after signing. This is the rule of strict performance. It reflects the idea that the parties allocated the risk of change when they made the contract.
Two routes depart from this rule: a force majeure clause written into the contract, and the common law doctrine of frustration. This chapter covers force majeure.
What force majeure is
Force majeure is a French term meaning "superior force." It describes an event beyond a party's control that stops or delays performance.
English law has no general doctrine of force majeure. A court excuses performance for such an event only if the contract says so. The wording of the clause therefore decides the outcome.
Anatomy of a force majeure clause
A typical clause contains these parts:
- Events: a list of named events, such as fire or flood, plus a catch-all phrase.
- Effect: the event must prevent, hinder, or delay performance.
- Causation: the event must actually cause the failure.
- Notice: the affected party must notify the other party within a set time.
- Consequences: suspension, extension of time, or termination.
Causation, burden and notice
The party relying on the clause usually bears the burden of proof. It must show that the event caused the failure, not just that the event happened. A missed notice deadline can defeat the claim even when the event is covered.
Reading the clause
Courts read a force majeure clause using ordinary principles of construction. They give the words their natural meaning in context. Specific listed events are read alongside general words. A catch-all phrase such as "any other event beyond reasonable control" is usually limited by the listed events. Courts often read it as covering events of a similar kind, not anything at all.
Exercise
A clause excuses delay "caused by" an event beyond reasonable control, and lists fire and flood. A supplier is late because a driver strike stopped its lorries, and a flood happened the same week but did not reach its depot. Is the supplier excused?
Show answer
Not clearly. The flood is irrelevant because it did not cause the delay. The strike is covered only if the catch-all reaches it, and the supplier must also prove causation and give timely notice.