Sub topic 3
Limits: foreseeability, express allocation of risk, self-induced frustration and cost increases
This chapter assumes you know the structure of a force majeure clause, the basic test for frustration, and what damages for breach mean.
Limits on frustration
Frustration does not excuse every disruption. Four limits apply.
- Foreseeability: If the parties foresaw the event, the risk was part of the bargain. In Davis Contractors v Fareham UDC (1956), delays of about eight years did not frustrate a building contract, because the work was not radically different from what was agreed.
- Express allocation: A clause that deals with the event governs it, and frustration is generally excluded.
- Self-induced frustration: A party cannot rely on a loss it caused. In Maritime National Fish v Ocean Trawlers (1935), the claimant's own choice of vessel led to the loss, so it could not claim frustration.
- Cost increases: Performance that is only more expensive is not radically different.
Consequences of frustration
Frustration ends the contract automatically when the event occurs. No notice is needed. The Law Reform (Frustrated Contracts) Act 1943 then governs money. Sums paid before frustration can be recovered, and sums due but unpaid stop being payable. The court may let the recipient keep expenses already incurred, and may order payment for a valuable benefit received.
Force majeure versus frustration
Read the express clause first. If it covers the event and its conditions are met, it applies. Frustration is the fallback when the contract does not deal with the risk and performance becomes radically different.
Case studies
- Pandemics: Outcomes depend on wording. A clause naming "epidemic" applies only if its notice and causation conditions are met.
- War and sanctions: In Tsakiroglou v Noblee Thorl (1962), closure of the Suez Canal did not frustrate a sale, because the goods could still be shipped by the longer Cape route.
- Supply disruption: A seller who can still obtain goods at higher cost usually remains bound.
Other legal systems
- US: UCC section 2-615 excuses sellers when performance becomes commercially impracticable. Restatement (Second) of Contracts section 265 covers frustration of purpose.
- Civil law: German BGB section 313 allows adjustment when the basis of a contract changes seriously. French Civil Code article 1195 allows renegotiation, and a court may revise or end the contract.
Putting it together
- Check the express clause: does the event fall within it, was notice given, and were mitigation duties met?
- If no clause applies, check whether the risk was foreseeable or allocated, or whether the party caused the event.
- Check whether the change is only a cost increase.
- If performance is radically different, frustration applies and the 1943 Act governs payments.
Exercise
A builder has a fixed-price contract, and the price of steel doubles because of a market shortage. Is the contract frustrated?
Show answer
Probably not. A cost increase alone does not make performance radically different, and a fixed-price contract usually allocates that risk to the builder. Check the express clause and foreseeability first.