Sub topic 2
Mitigation and Reasonable Endeavours Obligations
This chapter assumes you know the basic elements of a contract, the difference between express and implied terms, and what damages mean for breach.
Mitigation and reasonable endeavours
Many force majeure clauses require the affected party to mitigate, meaning it must take reasonable steps to reduce the effect of the event. Examples include sourcing an alternative supplier or rescheduling staff. A party need not take steps that are commercially unreasonable.
"Reasonable endeavours" is a weaker promise than an absolute obligation. It requires a genuine, good-faith effort, but not success. Courts often read "best endeavours" as demanding more than "reasonable endeavours," though English courts have been cautious about treating these phrases as fixed scales.
What happens next
Once a clause is triggered, the usual consequences are:
- Suspension: performance pauses while the event continues.
- Extension of time: deadlines move by the length of the delay.
- Termination: either party may end the contract if the event lasts beyond a stated period, often 90 days in illustrative clauses.
Payment obligations already due usually survive suspension.
Frustration: the doctrine and its rationale
Frustration is a common law doctrine. It applies when an event after the contract is formed makes performance radically different from what the parties agreed. The contract then ends automatically, and neither party is liable for later non-performance. The rationale is that the parties did not allocate the risk of the event, so the law discharges them.
The test: radical difference
Harder or more expensive performance is not enough. In Davis Contractors Ltd v Fareham UDC [1956] AC 696, the House of Lords held that a builder's contract was not frustrated merely because the work took longer and cost more than expected. The question is whether the performance would be radically different from what the parties undertook.
> Note: frustration does not apply where the event was foreseeable and the contract allocated the risk, or where the party relying on it caused the event itself.
Impossibility, illegality and frustration of purpose
Three categories recur:
- Impossibility: the subject matter is destroyed. In Taylor v Caldwell (1863), a music hall the parties had agreed to hire was destroyed by fire.
- Illegality: a change in law makes performance unlawful.
- Frustration of purpose: performance remains possible, but the shared purpose is defeated. In Krell v Henry [1903] 2 KB 740, a room was rented to view the coronation procession, which was cancelled. The contract was frustrated.
Exercise
A builder's contract is delayed because steel prices rise 20 percent. Is the contract frustrated?
Show answer
Probably not. A higher cost alone does not make performance radically different, as Davis Contractors shows, unless the clause or the circumstances say otherwise.