Solution Scope and Change Control
This chapter assumes you know the Explore phase, scope items, and the difference between fit, configuration, and delta findings from earlier chapters. It covers how the agreed solution scope is protected once workshops start producing findings.
What solution scope means after the workshops
The solution scope is the list of scope items, organizational units, and approved delta requirements that the project will deliver. Workshops test that scope against real business needs. Every finding either stays inside the scope or pushes against it.
Scope pressure usually shows up in three ways:
- A user asks for a process that no selected scope item covers.
- A delta requirement grows during discussion until it becomes a small project.
- A "must-have" is raised late, after estimates were prepared.
Without a rule for these cases, the scope changes silently and the budget and schedule follow.
Change control in a fit-to-standard project
Change control is the agreed route for deciding whether a new or altered requirement enters the scope. It does not block change. It makes each change visible, assessed, and approved by someone with authority.
A workable route has five steps:
- Record the request with its business justification.
- Check whether a standard scope item or configuration already covers it.
- Review extensibility options in order of preference, consistent with the clean core.
- Estimate effort, cost, and effect on the timeline.
- Obtain a decision from the agreed approver and update the scope baseline.
Step 2 matters most. Many requests that look like scope additions turn out to be configuration inside an existing scope item.
Recording a scope change
A scope change should reference the workshop finding it came from, so traceability is kept. The record below is illustrative and tool-neutral.
{
"id": "CR-021",
"originFinding": "F2S-SD-007",
"request": "Add a customer-specific document layout for a second key customer",
"scopeImpact": "Extends an approved delta requirement",
"cleanCoreCheck": "In-app and key user extensibility reviewed first",
"estimateStatus": "to be estimated",
"decisionOwner": "Project steering committee",
"decision": "pending"
}The fields link the change to its origin, show that the clean core was checked, and name who decides.
Common errors
- Treating the workshop as the approval. A workshop records a need. Only the change route approves it.
- Skipping the baseline. Without a signed starting scope, you cannot show what changed.
- Estimating before the clean core check. This can price a custom build when a standard option existed.
- Closing rejected requests without a reason. The same request returns in the next workshop.
Exercise
During a finance workshop, a user asks for a report that existing standard apps may already provide. Which step of the change route applies first, and why?
Show answer
Step 2, checking whether a standard scope item or configuration already covers the request. If it does, no scope change is needed and the finding is recorded as fit or configuration. Estimating or approving a custom build before this check risks paying for something the standard already offers.