Outputs, Review, and Sign-Off
This chapter assumes you know the fit-to-standard workflow, the fit, configuration, and delta classification, and how findings reach the backlog. It covers what a workshop series must hand over, how the team reviews it, and how sign-off closes the Explore phase.
What the workshops produce
Each workshop series should leave a small, consistent set of outputs. Every item must trace back to a scope item and a process step.
- Findings log: every finding classified as fit, configuration, or delta.
- Configuration decisions: the values and choices the business agreed on.
- Delta requirements: each with a justification, a proposed extensibility approach, and a priority.
- Confirmed solution scope: the scope items the project will deliver.
- Open issues and actions, each with an owner and a due date.
The record below shows a finding that is ready for review. It has an ID, a classification, a decision, an owner, and a status.
{
"id": "F2S-FI-014",
"scopeItem": "Accounts Payable",
"processStep": "Post vendor invoice",
"finding": "Business requires a second approval for invoices above a company-specific threshold",
"classification": "configuration",
"decision": "Evaluate the standard approval workflow options before proposing any custom development",
"owner": "Finance process lead",
"status": "open"
}The review cycle
Raw workshop notes are not a deliverable. After each session, the workshop facilitator and the process lead clean up the findings log. They check that every entry has a classification, an owner, and a status. Business participants then review the entries for their own area and confirm that the notes reflect what was said.
Review also checks consistency across workshops. Two areas may record conflicting decisions for the same shared object, such as the business partner or the chart of accounts. Resolve these conflicts before sign-off, not during Realize.
Sign-off
Sign-off is the business confirming that the recorded results are accurate and complete enough to build on. It usually covers three things:
- The configuration decisions for each scope item.
- The list of approved delta requirements and their priorities.
- The solution scope, including items deliberately left out.
After sign-off, the results become a baseline. Later changes go through the change control process described in the previous chapter, so the team can see what changed and why.
Common errors
- Signing off notes that still contain unclassified findings.
- Leaving delta requirements without a justification, which makes estimating and prioritizing hard.
- Approving open items with no owner, so they stay open until Realize.
- Keeping outputs in separate files per workshop, which breaks traceability to the backlog.
Exercise
A finance workshop ends with 20 findings. Three have no classification, and two deltas have no business justification. Should the process lead request sign-off now? Explain.
Show answer
No. Unclassified findings and unjustified deltas make the output incomplete. The team should classify the three findings and add justifications (or drop the deltas) first. Then the business reviews the corrected entries, and only after that does sign-off create a reliable baseline.