Sub topic 18
Common pitfalls and how to avoid them
This chapter assumes you know the Explore phase, scope items, the starter system, and the fit, configuration, and delta classification. It covers the mistakes that most often weaken a fit-to-standard workshop series, and how to prevent each one.
Pitfalls in preparation
Most workshop problems start before the first session.
- Unprepared attendees. Business users who have never seen the standard process spend the session reacting, not deciding. Send the scope item description and a short agenda ahead of time.
- Wrong people in the room. If nobody can make decisions for the process area, findings stay open. Confirm that each session has a process owner who can accept or reject a standard approach.
- Poor demo data. A demo with unrealistic data hides the cases users care about. Load representative customers, materials, and vendors into the starter system before the workshop.
- Scope drift. Walking through processes that are not in scope wastes time. Keep the agenda tied to the selected scope items.
Pitfalls during the workshop
- Treating the session as a blueprint. Teams collect long requirement lists without ever showing the standard process. Demonstrate first, then ask what does not fit.
- Jumping to custom development. A user says "we do it differently" and the team logs a delta at once. Ask why the current process exists. Many gaps are habits, not needs.
- Misclassifying findings. A configuration item recorded as a delta inflates the estimate. A real delta recorded as a fit surfaces late, during Realize. Check each finding against the scope item's configuration options before classifying it.
- Missing configuration values. "Approval needed above a threshold" is not useful without the threshold. Record the value, the owner, and the decision.
Pitfalls after the workshop
- Lost traceability. Findings that live only in meeting notes cannot be linked to the backlog. Give every finding an ID, a scope item, and a status.
- Unreviewed deltas. A delta needs a business justification and an extensibility option reviewed against the clean core principle before it is estimated.
- Silent scope changes. A delta accepted informally changes the solution scope. Route it through change control.
- Sign-off without review. Approving outputs nobody has read moves the risk to later phases.
Example of a well-formed record
A finding that avoids most of these pitfalls is complete, classified, and owned.
{
"id": "F2S-FI-014",
"scopeItem": "Accounts Payable",
"processStep": "Post vendor invoice",
"finding": "Business requires a second approval for invoices above a company-specific threshold",
"classification": "configuration",
"decision": "Evaluate the standard approval workflow options before proposing any custom development",
"owner": "Finance process lead",
"status": "open"
}The record names the scope item and process step. It carries a classification, a decision, an owner, and a status, so it can be traced into the backlog.
Quick reference
| Pitfall | Typical effect | Prevention |
|---|---|---|
| Unprepared attendees | Slow, reactive sessions | Send materials in advance |
| Custom development first | Inflated delta list | Ask why, check configuration |
| Missing values | Rework in Realize | Record values and owners |
| Informal scope changes | Budget and timeline drift | Use change control |
Exercise
A key user says the standard purchase approval does not match how the department works, and a team member immediately logs a delta requirement. Which pitfall is this, and what should the team do first?
Show answer
This is jumping to custom development. The team should first ask why the current process exists, then check whether standard configuration or the standard approval workflow covers the need. Only if a real gap remains should it become a delta, with a business justification and an extensibility option reviewed against the clean core principle.