From Effort to Calendar Time: People, Focus and Availability
Assume you know basic project terms such as task, milestone, deliverable, and schedule. This chapter focuses on turning estimated effort into working days on a calendar.
Effort, duration, and elapsed time
Effort is the amount of work required. It is often measured in person-hours or person-days. One person-day means one person working for one full working day.
Duration is the time a task takes from start to finish. Elapsed time is the calendar time that passes, including weekends, holidays, waiting, and interruptions.
These values differ:
- A task may require 20 person-days of effort.
- Two people may work on it.
- Each person may spend only 70% of each workday on it.
- The resulting duration is about 15 working days.
Use this formula when the work can be divided effectively:
Duration in working days = effort in person-days / (people × focus factor)
The focus factor is the share of a person's working time available for the task. A factor of 1.0 means full-time focus. A factor of 0.5 means half-time focus.
A worked conversion
Suppose a task requires 20 person-days. Two people are assigned, but meetings, support work, and other projects reduce their focus to 70%.
Duration = 20 / (2 × 0.7) = 14.29 working days
Round up to 15 working days. Rounding down would promise work before the calculated effort can be completed.
| Input | Value | Meaning |
|---|---|---|
| Effort | 20 person-days | Total work required |
| People | 2 | People assigned to the task |
| Focus factor | 0.70 | Share of each day available |
| Duration | 15 working days | Rounded calendar estimate |
Availability is not the same as team size
Adding people does not always reduce duration in direct proportion. People may need time to coordinate, review each other's work, or learn the system. Some tasks also contain work that only one person can perform.
For example, assigning four people to a task estimated at 10 person-days does not guarantee completion in 2.5 days. A realistic focus factor might be lower because coordination increases. Use the availability assumption that matches the actual team.
Use a small calculation
This Python function converts effort into whole working days. It rounds up because a partial working day still occupies a calendar day.
from math import ceil
def calendar_days(effort_person_days, people, focus_factor):
if people <= 0:
raise ValueError("people must be greater than zero")
if not 0 < focus_factor <= 1:
raise ValueError("focus_factor must be between 0 and 1")
return ceil(effort_person_days / (people * focus_factor))
days = calendar_days(20, 2, 0.7)
print(f"{days} working days")This result still needs calendar adjustments. A 15-working-day task may span more than 15 elapsed days if it crosses weekends, holidays, planned leave, or waiting periods.
Exercise
A task requires 30 person-days. Three people are assigned, and each can give 80% of a working day to the task. What whole number of working days should you plan?
Show answer
Calculate 30 / (3 × 0.8) = 12.5. Round up to 13 working days, then check for weekends, holidays, dependencies, and other waiting time.