Estimating as a Group: Expert Judgment, Delphi, and Planning Poker
Assume you know basic project terms such as task, deliverable, milestone, and schedule. This chapter focuses on choosing and combining estimates from several people. It assumes that the work has already been divided into tasks that are small enough to discuss.
Group estimation can improve accuracy because a team brings different experience, questions hidden assumptions, and notices risks that one person may miss. It can also fail when senior people dominate, participants anchor on the first number, or the group confuses agreement with accuracy.
Expert judgment
Expert judgment is an estimate based on the experience of someone familiar with similar work. The expert should explain the assumptions behind the number, not just provide a number.
Ask questions such as:
- What previous work are you comparing this with?
- What is included and excluded?
- Which part is most uncertain?
- What would make this take twice as long?
- Does the estimate describe effort or calendar duration?
Record the estimate, assumptions, and confidence. This makes later comparison possible.
Delphi estimation
The Delphi method collects estimates independently before discussion. A facilitator asks each participant for an estimate and reasoning, usually without revealing names. The group then reviews the spread, discusses differences, and estimates again.
Delphi works well when the team has mixed experience or when hierarchy could affect responses. It takes more time than simply asking for a consensus. The facilitator should focus discussion on evidence, dependencies, and scope rather than on defending personal estimates.
Planning poker
Planning poker is a structured form of group estimation. Participants choose cards privately, reveal them at the same time, and explain unusually high or low values. The team repeats the vote until it reaches a useful shared estimate.
It is often used with relative units such as story points. The points represent comparison, not hours. For example, a task rated 8 is expected to require about twice the overall effort or uncertainty of a task rated 4. The team must define a reference task first.
| Technique | Best use | Main risk |
|---|---|---|
| Expert judgment | A specialist has strong relevant experience | Overconfidence or hidden assumptions |
| Delphi | Independent views are important | Slow convergence |
| Planning poker | A delivery team needs shared relative estimates | False consensus or point-to-hour conversion |
Making group estimates useful
Use these practices:
- Estimate the same scope and unit.
- Separate effort from duration.
- Ask the highest and lowest estimators to explain their reasoning.
- Investigate disagreement instead of averaging it away.
- Stop when the estimate is good enough for the decision.
- Record a range when uncertainty remains.
- Revisit the estimate when scope, dependencies, or technology changes.
Exercise
Exercise
Three people estimate a task as 2, 3, and 8 days. What should the facilitator do before averaging these values?
Show answer
Ask the estimator who chose 8 and the estimator who chose 2 to explain their assumptions, then check whether they estimated the same scope, risks, and unit.