Sub topic 1
Effort, Duration and Elapsed Time: What You Are Actually Estimating
Prerequisites
Assume you know the basic project terms task, milestone, deliverable, and schedule. You should also be comfortable with averages and simple division. This chapter focuses on the difference between how much work exists and how long that work takes on a calendar.
Three Different Measures
Effort is the amount of work required. Teams often measure it in person-hours or person-days. One person-day means one person working for one normal working day.
Duration is the time a task takes from start to finish while someone is actively working on it. A task requiring 16 person-hours has a duration of two working days if one person works on it full time.
Elapsed time is the calendar time between the planned start and finish. It includes weekends, holidays, waiting, reviews, handoffs, and other delays. A task with two working days of duration might have four days of elapsed time if it starts on Friday and finishes on Monday.
| Measure | Meaning | Example |
|---|---|---|
| Effort | Total work required | 16 person-hours |
| Duration | Active working time | 2 working days for one person |
| Elapsed time | Calendar time from start to finish | 4 calendar days |
Do not convert effort directly into a delivery date without considering people, availability, dependencies, and interruptions.
Converting Effort to Duration
A simple conversion is:
duration = effort / (number of people × focus factor)
The focus factor is the share of each person's working time available for this task. A factor of 0.7 means that 70 percent of working time is available after meetings, support work, context switching, and other obligations.
from math import ceil
def calendar_days(effort_person_days, people, focus_factor):
"""Return working days needed for independent parallel work."""
if effort_person_days < 0 or people <= 0 or not 0 < focus_factor <= 1:
raise ValueError("Use nonnegative effort, positive people, and a focus factor from 0 to 1.")
return ceil(effort_person_days / (people * focus_factor))
print(calendar_days(20, 2, 0.7)) # 15 working daysThis calculation assumes the work can be divided effectively between the people. Adding people does not always shorten duration. Some tasks cannot be split, and coordination can create extra effort. A task may also depend on another task finishing first.
Common Errors
- Reporting “five days” without saying whether that means five person-days or five calendar days.
- Assuming every assigned person is available full time.
- Treating parallel work as automatically independent.
- Ignoring review, approval, environment, or handoff delays.
- Rounding down and creating a date that has no practical margin.
State the unit and assumptions with every estimate. For example: “The task requires 12 person-days of effort. Two developers are available at a 60 percent focus factor, so the active duration is about 10 working days before review and dependency delays.”
Exercise
A task requires 18 person-days. Two people can spend 75 percent of their time on it. What is the approximate working duration?
Show answer
12 working days, calculated as 18 / (2 × 0.75). Add elapsed time if reviews, dependencies, weekends, or holidays affect the schedule.