Sub topic 11
From Effort to Calendar Time: People, Focus and Availability
This chapter assumes you can already estimate effort for a task in person-days, using the techniques from the earlier chapters. It also assumes you know the difference between effort and duration. Here you will learn to turn an effort figure into working days and then into a calendar date.
The core conversion
Effort is the amount of work, measured in person-days. Duration is how many working days pass while that work gets done. The basic relationship is:
duration (working days) = effort / (people x focus factor)The focus factor is the share of a working day a person actually spends on this work. Meetings, email, support requests, code reviews for other teams and switching between tasks all take time away from it. A focus factor of 1.0 means a person works on the task for every working hour. In practice, values between 0.6 and 0.8 are common for project work.
from math import ceil
def calendar_days(effort_person_days, people, focus_factor):
# focus_factor: share of a working day each person spends on this work
return ceil(effort_person_days / (people * focus_factor))
print(calendar_days(20, 2, 0.7)) # 15 working daysTwenty person-days with two people at 0.7 gives 20 / 1.4 = 14.3, which rounds up to 15 working days. Always round up. A task cannot finish in 0.3 of a day, and a fractional day of leftover work still has to be done.
Focus factor: measure it, don't guess it
Teams often use 1.0 because it is convenient, and every schedule then runs late. Estimate the focus factor from evidence:
- Take a typical week for the people on the work.
- Subtract recurring meetings, support rotations, training and administration.
- Divide the hours left for project work by the total working hours.
If someone has 40 hours a week and 12 of them go to other duties, their focus factor is 28 / 40 = 0.7. Later, you can check the figure against your actuals (a later chapter covers calibration).
The focus factor is a property of the person and the period, not of the task. A person on-call this week has a lower value than the same person next week.
Availability: not everyone contributes equally
Real teams are uneven. One person is full-time, another is allocated at 50%, a third joins in week two. Handle this by computing a capacity for each person, in person-days of project work per working day, and then adding the capacities.
from math import ceil
# (allocation, focus_factor) per person
team = [(1.0, 0.7), (0.5, 0.7)]
capacity = sum(allocation * focus for allocation, focus in team)
effort = 20 # person-days
print(f"capacity: {capacity:.2f} person-days per working day")
print(f"duration: {ceil(effort / capacity)} working days")The capacity is 0.70 + 0.35 = 1.05 person-days per working day, so 20 person-days take 20 / 1.05 = 19.05, which rounds up to 20 working days. Counting this as "1.5 people" would give 20 / 1.5 = 13.3 days, and the plan would be wrong by more than a week.
Skills matter as well. Capacity only adds up across people who can do the work. Two spare designers do not shorten a database migration.
Adding people does not divide the time
The formula suggests that doubling the people halves the duration. It does not, for three reasons.
- Communication overhead. The number of pairwise communication paths among n people is n(n - 1) / 2. It grows much faster than headcount.
- Onboarding. A new person needs time to learn the context, and an existing team member usually spends time teaching them. During that period total capacity may go down.
- Indivisible work. Some work cannot be split. If a task needs one person's judgment for ten days, ten people will not finish it in one day.
| People | Communication paths |
|---|---|
| 2 | 1 |
| 3 | 3 |
| 5 | 10 |
| 8 | 28 |
Duration is not always effort divided by capacity
Some parts of a schedule do not follow the formula at all.
- Fixed-duration activities. A compliance review, a data load or a vendor lead time takes the same time whether you have 1 person or 10. Estimate them directly in days.
- Waiting time. Time spent waiting for an approval, a delivery or someone else's answer consumes calendar time but no effort. Estimate it separately and add it to the schedule.
- Minimum duration. If one person must do a piece of work, the duration cannot be shorter than that person's effort divided by their own focus factor, regardless of team size.
For these reasons, estimate effort-driven tasks with the formula and treat fixed or waiting activities as separate line items. Mixing them in one number hides which part of the estimate is soft.
From working days to calendar dates
The formula gives working days. A stakeholder wants a date. Between the two sit weekends, public holidays and planned leave. The function below counts forward from a start date and skips non-working days.
from datetime import date, timedelta
def finish_date(start, working_days, holidays=frozenset()):
"""Return the date on which the last of `working_days` is completed.
The start date counts as day 1 if it is a working day.
"""
day = start
done = 0
while True:
if day.weekday() < 5 and day not in holidays:
done += 1
if done == working_days:
return day
day += timedelta(days=1)
start = date(2026, 12, 7) # a Monday
holidays = {date(2026, 12, 25)} # a Friday
print(finish_date(start, 15).isoformat()) # 2026-12-25
print(finish_date(start, 15, holidays).isoformat()) # 2026-12-28Fifteen working days from Monday 7 December end on Friday 25 December. When 25 December is a holiday, the work finishes on Monday 28 December. Individual absences work the same way, but they reduce one person's capacity instead of closing the whole calendar. Subtract the leave days from that person's availability for the period.
Common errors
- Using 1.0 as the focus factor. This is the most frequent cause of schedules that slip steadily from week one.
- Counting part-time people as whole people. Use allocation times focus for each person.
- Applying the formula to a range instead of a point. If your effort is a PERT range, convert both ends (and the 90% figure) separately. Do not convert only the expected value and present it as a promise.
- Ignoring ramp-up. A person joining mid-project contributes less for the first days.
- Forgetting that dates move with the calendar. The same 15 working days finish at different dates depending on holidays, so recompute the date when the start changes.
Exercise
A task has an estimated effort of 45 person-days. Three people will work on it, and each has a focus factor of 0.6. How many working days will it take?
Show answer
Capacity is 3 x 0.6 = 1.8 person-days per working day. Duration is 45 / 1.8 = 25 working days. No rounding is needed, because the result is a whole number.
Exercise
A team lead says, "This task needs 10 person-days, so with 10 people we can finish it in one day." Give two reasons this is unlikely to hold.
Show answer
Any two of these are valid. Communication overhead grows faster than headcount (10 people have 45 communication paths). New people need onboarding time. The work may not be divisible into ten independent pieces. Each person's focus factor is below 1.0, so ten people give less than ten person-days per day. Waiting or fixed-duration steps do not shrink with more people.
Exercise
A project needs 30 person-days of effort, 2 working days of vendor lead time that cannot overlap the work, and starts on a Monday with two people at 0.75 focus. Assuming no holidays, how many working days does it take in total?
Show answer
Capacity is 2 x 0.75 = 1.5 person-days per working day. The effort-driven duration is 30 / 1.5 = 20 working days. Adding the 2 working days of vendor lead time gives 22 working days in total.