Sub topic 3
Breaking work down so it can be estimated
This chapter assumes you know basic project vocabulary (task, milestone, deliverable) and understand the difference between effort and duration. It covers how to split a project into pieces small enough to estimate, and how to check that the split is sound.
Why estimate pieces instead of the whole
You can't estimate "build the customer portal" with any confidence. The scope is large, the unknowns are buried inside it, and any single number hides them. A smaller piece such as "build the password reset form" is something you or a colleague has probably done before, so you can reason about it.
Breaking work down helps in four ways:
- It exposes work nobody had listed, such as data migration, accessibility review or deployment.
- It turns one large guess into many smaller ones. Their errors partly cancel when summed (the next chapters on bottom-up and three-point estimation cover this).
- It gives each piece a clear owner and a clear definition of done.
- It supplies the task list that dependency and critical-path analysis needs later.
The work breakdown structure
A work breakdown structure (WBS) is a hierarchical decomposition of the total scope of a project into smaller and smaller pieces. The top level is the whole project. Each level splits its parent into parts. The lowest level holds the pieces you actually estimate and assign. Those lowest-level pieces are often called work packages or leaf tasks.
Only the leaves carry estimates. A parent's figure is the sum of its children and is never estimated on its own. If you estimate both a parent and its children, you will eventually have two numbers that disagree, and you won't know which to trust.
Two ways to decompose
The usual choice is between decomposing by deliverable and decomposing by phase.
| Approach | Top-level branches look like | Strength | Weakness |
|---|---|---|---|
| By deliverable (product-oriented) | Login, Billing, Reporting | Matches what stakeholders asked for. Easy to check scope. | Shared work such as testing or deployment can fall between branches. |
| By phase (process-oriented) | Design, Build, Test, Release | Matches how the team works. Easy to assign by skill. | Hides which features are costly. Late phases get forgotten or squeezed. |
A common compromise is to split by deliverable at the top and by activity underneath. Under "Billing" you would then have design, build and test leaves. Whatever you choose, keep one rule at each level. Don't mix deliverables and phases among siblings, or the branches will overlap.
The 100% rule
The 100% rule says that the children of any node must cover 100% of the parent's scope, and nothing outside it. Two failures follow from breaking it:
- Gaps. Work exists that no leaf covers, so it is never estimated. Typical gaps are environment setup, data migration, documentation, project management and rework after review.
- Overlap. The same work appears under two leaves. It is estimated twice and may be done twice.
To check, read each parent and ask two questions: "If every child were finished, would the parent be finished?" and "Does any child contain work that belongs elsewhere?"
How small is small enough
Stop decomposing when a leaf meets these tests:
- One person or pair could own it. If it needs three skill sets in sequence, split it.
- It has an observable finish. "Password reset sends an email and lets the user set a new password" is checkable. "Work on login" is not.
- Someone can say what is most likely to go wrong. If nobody can, the leaf is either too vague or too unfamiliar.
- It fits a size band. Many teams use a band such as half a day to about two weeks of effort. Pick a band and apply it consistently.
Both ends of the band cost something. Leaves that are too large carry hidden sub-tasks and wide uncertainty. Leaves that are too small, such as 30-minute tasks, make planning slow, create false precision and drown the plan in bookkeeping. Detail should match what you know. Near-term work can be broken down finely, and work that is months away can stay coarse until you learn more. This approach is sometimes called rolling-wave planning.
Checking a breakdown with code
A small script can enforce the size band and total the leaves. The numbers below are effort in person-days.
wbs = {
"Customer portal": {
"Login": {"Sign-in form": 2, "Password reset": 3},
"Billing": {"Invoice list": 4, "Payment integration": 15},
"Release": {"Deployment pipeline": 3, "Acceptance testing": 5},
}
}
MAX_LEAF_DAYS = 8
def leaves(node, path=()):
for name, child in node.items():
if isinstance(child, dict):
yield from leaves(child, path + (name,))
else:
yield path + (name,), child
total = 0
for path, days in leaves(wbs):
flag = " <- split further" if days > MAX_LEAF_DAYS else ""
print(f"{' > '.join(path)}: {days} days{flag}")
total += days
print(f"total: {total} days")Running it prints one line per leaf and flags "Payment integration" at 15 days. That is a prompt to decompose it, for example into provider account setup, payment form, webhook handling, refund flow and failure testing. After splitting, the total often rises, because the finer view shows work the coarse leaf hid. That rise is a gain in accuracy and not a sign that the breakdown went wrong.
Common errors
- Decomposing by guessing the number first. If you pick a target total and then divide it among leaves, you have a budget and not an estimate.
- Uneven depth without reason. One branch broken to one-day leaves and another left at 20-day leaves means the second branch is where your risk sits. Look at it again.
- Splitting by who does it. Leaves like "Alice's tasks" make the plan fall apart when people change.
- Leaves that are activities with no output. "Testing" or "Meetings" with no scope cannot be checked. Tie each to something specific, such as "Regression test of billing flows".
- Treating the WBS as a schedule. The WBS says what the work is, not in what order it happens. Sequence and dependencies come later.
- Freezing it. Revisit the WBS when scope changes or when you learn something. A WBS that was right in week 1 can be wrong in week 6.
A short procedure
- Write the project's goal and its main deliverables as the first level.
- Split each deliverable into components, using one splitting rule per level.
- Continue until each leaf passes the size tests above.
- Add the cross-cutting work (setup, review, release, handover, management) as its own branches or leaves.
- Apply the 100% check from the bottom up.
- Have someone who did not build the WBS read it. A fresh reader finds gaps quickly.
- Record assumptions next to leaves where scope is open to interpretation.
Exercise
A WBS for a mobile app has leaves "Design", "Development", "Testing" and "Bug fixing", each estimated at 20 days, and a leaf "Push notifications" at 6 days. Name two problems with this breakdown and how you would fix them.
Show answer
First, the sibling leaves mix phases (Design, Development, Testing, Bug fixing) with a feature (Push notifications), so the branches overlap. Push notifications also involves design, development and testing, so its effort is probably counted twice or left ambiguous. Fix this by choosing one rule per level, such as deliverables at the top (for example Core screens, Push notifications) and activities underneath. Second, the 20-day leaves are too large and have no observable finish ("Development" and "Bug fixing" in particular). Split them into feature-level leaves of roughly half a day to two weeks, each with a clear done condition, and give "Bug fixing" a defined scope such as fixes from a specific test round.