Bottom-up estimation: summing task estimates
Bottom-up estimation builds a project estimate from the smallest pieces of work. You list the tasks, estimate each one, and add the results upward through the work breakdown structure (WBS). This chapter assumes you can already break a project into a WBS, tell effort from duration, and read a three-point estimate. Those topics are covered in earlier chapters.
When bottom-up fits
Bottom-up is usually the most accurate technique, but it is also the most expensive. It needs a defined scope and a task list, so it suits the middle and later stages of planning, when the work is known well enough to name. Early in a project, analogous or parametric estimates are cheaper and more honest, because the detail bottom-up needs does not exist yet.
Use it when:
- the scope is stable enough to list deliverables
- someone who will do the work can judge each task
- the estimate will become a commitment, such as a budget, a contract or a schedule baseline
The procedure
- Decompose the scope until each leaf (a work package) is small enough to estimate with confidence.
- Estimate effort for each leaf, ideally with a range or a three-point estimate.
- Add the leaf estimates into their parent nodes, then into the project total.
- Add the work that no leaf captures: coordination, integration, rework and management.
- State assumptions and convert effort to duration separately.
Choosing the leaf size
Leaf size is the main decision in bottom-up work. Too coarse and each estimate hides unknowns. Too fine and you spend days estimating, and the numbers look more precise than they are.
A common heuristic is that a leaf should take between about one day and ten days of effort. Treat that as a starting point, not a rule. A better test is whether the person estimating can describe the steps of the task. If they cannot, decompose further or run a small investigation first.
Check the leaves against these questions:
- Is there one owner who could do it?
- Is there a clear "done" condition?
- Would two people give roughly the same estimate?
If two people disagree by a factor of three or more, the task is probably unclear, not hard. Resolve the scope question before averaging the numbers.
A runnable roll-up
The script below stores the WBS as nested dictionaries, with effort in person-days at the leaves. It sums recursively, prints each level, and adds a coordination allowance as a separate line.
wbs = {
"Backend": {"Payment API": 6.0, "Order model": 3.0, "Webhooks": 4.0},
"Frontend": {"Checkout form": 5.0, "Error states": 2.0},
"Quality": {"Integration tests": 3.0, "Security review": 1.0},
}
COORDINATION_RATE = 0.10 # meetings, reviews, hand-offs, as a share of task effort
def roll_up(node):
if isinstance(node, dict):
return sum(roll_up(child) for child in node.values())
return node
def report(node, name="Project", depth=0):
print(f"{' ' * depth}{name}: {roll_up(node):.1f}")
if isinstance(node, dict):
for child_name, child in node.items():
report(child, child_name, depth + 1)
report(wbs)
task_total = roll_up(wbs)
allowance = task_total * COORDINATION_RATE
print(f"Coordination allowance: {allowance:.1f}")
print(f"Project effort: {task_total + allowance:.1f} person-days")The output is:
Project: 24.0
Backend: 13.0
Payment API: 6.0
Order model: 3.0
Webhooks: 4.0
Frontend: 7.0
Checkout form: 5.0
Error states: 2.0
Quality: 4.0
Integration tests: 3.0
Security review: 1.0
Coordination allowance: 2.4
Project effort: 26.4 person-daysKeeping the allowance as its own line makes it visible and open to challenge. If you folded it into each task, nobody could tell later how much was padding.
What bottom-up estimates miss
A bottom-up total is only as complete as the task list. The most common failure is not a bad estimate of a listed task. It is a task that nobody listed. Studies of overruns repeatedly find that omitted work accounts for a large share of the error.
Check the WBS for these categories:
- Integration of components built by different people
- Code review, design review and approval waits
- Environment setup, data migration and deployment
- Documentation, training and hand-over
- Defect fixing after testing (rework)
- Project management, status reporting and stakeholder meetings
Some of these can be listed as leaves. Others are better handled as a percentage allowance, like the coordination rate in the script. Whichever you choose, record which method you used.
Summing ranges, not single numbers
If every leaf is a single number, the total looks exact and carries no information about risk. Prefer three-point estimates at the leaf level, then sum the expected values.
Do not sum the most likely values. Task durations are usually right-skewed, because a task can run much longer than planned but rarely finishes much faster. With the three tasks from the PERT chapter, the most likely values are 4, 5 and 2 days, which sum to 11 days. The PERT expected values are 5.0, 6.0 and 2.3 days, which sum to 13.3 days. The gap of more than two days is skew, and the sum of most likely values ignores it.
The variances add as well, under an independence assumption: the project's standard deviation is the square root of the sum of the task variances. Independent errors partly cancel, so the total's spread is smaller in relative terms than any one task's.
Common errors
| Error | Symptom | Counter |
|---|---|---|
| Omitted tasks | Total looks fine but the project overruns on work nobody planned | Review the WBS against a checklist of work categories and against a past project's WBS |
| Summing most likely values | Total is below the expected value | Use expected values, or at least state that the total is a "most likely" figure |
| Padding each task | Totals are inflated and padding is spent on easy tasks | Estimate honestly per task and add contingency once, at a higher level |
| Double counting | Review or test effort appears in both a parent allowance and the leaves | Define each allowance and say what it covers |
| False precision | Estimates like 3.37 days | Round to the precision of your knowledge, such as half days |
| Estimating alone | One person's blind spots go uncorrected | Have the doer estimate, then have a peer review |
| Mixing units | Some leaves are person-days and others calendar days | Fix one unit for the whole WBS |
Checking the result
A bottom-up estimate should not be the only number you look at. Cross-check it:
- Compare it with an analogous estimate from a similar finished project. If the two differ by more than about 30 percent, find out why before trusting either.
- Compare the share of effort per category with past projects. Testing at 5 percent of effort, when similar projects run at 25 percent, suggests missing tasks.
- Ask the team whether the total feels plausible. A strong reaction in either direction is evidence about something the numbers hide.
Keeping the estimate usable
Record what you assumed with each leaf: the skill level of the person who will do it, the availability of dependencies, and any technology the team has not used before. When an assumption fails, you can then see which leaf to revise instead of arguing about the total.
Store the leaf estimates in a form you can compare with actuals later. The calibration chapter relies on this record to find which kinds of tasks you underestimate.
Exercise
A WBS has leaves with effort estimates of 3, 5, 2 and 6 person-days, all of them most likely values. Review effort is not a leaf. The team's past projects spent about 15 percent of task effort on reviews and hand-offs. What is the bottom-up effort including the allowance, and why might this total still be too low?
Show answer
The leaves sum to 16 person-days. The 15 percent allowance adds 2.4, so the total is 18.4 person-days. It may still be too low because the leaf values are most likely values, not expected values. If the tasks are right-skewed, their expected values sum to more than 16. The task list could also omit work, such as integration or deployment. A shared bias in the estimates would not cancel out either.
Exercise
Two estimators give leaf estimates of 2 days and 7 days for the same task. Should you average them to 4.5 days?
Show answer
No. A spread this wide usually means the estimators have different pictures of the scope. Find the cause first: clarify the task, split it into smaller leaves, or run a short investigation. Averaging hides the disagreement without resolving it.