Sub topic 1
Why Earned Value: Measuring Progress in Money Terms
Prerequisites
This chapter assumes you know basic project vocabulary (scope, schedule, budget, milestone), can read a work breakdown structure, and are comfortable with percentages and simple spreadsheet arithmetic.
Why earned value
Schedule and budget reports often answer only "Are we on time?" or "Have we spent the money?" Earned value management (EVM) answers a harder question: how much planned work is actually complete, measured in money. It compares three values: planned value (PV), earned value (EV), and actual cost (AC). The rest of this chapter builds the first and most basic of these, starting from the plan.
The performance measurement baseline
The performance measurement baseline is the approved plan that EVM measures against. It combines scope, schedule, and budget into one time-phased budget. Each period of the project gets a planned budget, and the sum of those budgets is the total planned cost. Without a fixed baseline, progress numbers drift and cannot be compared across reporting periods.
Work packages and control accounts
A work breakdown structure (WBS) splits the project into smaller pieces of work. A work package is the lowest level of the WBS where you assign a budget and a schedule. A control account groups several work packages under one manager. Costs are collected at the work-package level, then rolled up to the control accounts.
Planned value and budget at completion
Planned value is the budgeted cost of the work scheduled to be done by a given date. Budget at completion (BAC) is the total of all planned values across the project. Summing the work-package budgets gives BAC:
work_packages = [
{"name": "Design", "budget": 20000},
{"name": "Build", "budget": 50000},
{"name": "Test", "budget": 30000},
]
bac = sum(wp["budget"] for wp in work_packages)
print(bac) # 100000The diagram shows how these pieces connect.
Exercise
The Build package budget rises from 50000 to 60000, while Design stays at 20000 and Test at 30000. What is the new BAC?
Show answer
110000, because 20000 + 60000 + 30000 = 110000.