Sub topic 2
Deciding how much work counts as done
This chapter assumes you know work packages, planned budgets by task, and basic ratio arithmetic. Earned value (EV) depends on a rule for when work counts as done, so you need that rule before any other EVM number is meaningful.
Choosing a completion rule
Each work package needs a rule that sets its percent complete. Common rules include:
- 0/100: Credit zero until the package is finished, then credit all of it.
- 50/50: Credit half the budget when work starts and the rest when it finishes.
- Weighted milestones: Assign each milestone a share of the budget and credit the shares as they are reached.
- Percent complete: Estimate the fraction of work done. This is the most flexible rule and the easiest to inflate.
Pick the rule before work starts and record it in the baseline.
Earned value and actual cost
Earned value (EV) is the budget of the work completed: each package's budget multiplied by its completed fraction. Actual cost (AC) is what that work really cost, taken from accounting records.
work_packages = [
{"name": "Design", "budget": 20000, "percent_complete": 1.00},
{"name": "Build", "budget": 50000, "percent_complete": 0.40},
{"name": "Test", "budget": 30000, "percent_complete": 0.00},
]
bac = sum(wp["budget"] for wp in work_packages)
ev = sum(wp["budget"] * wp["percent_complete"] for wp in work_packages)
pv = 50000 # planned value at the status date, from the baseline
ac = 45000 # actual cost from accounting
sv = ev - pv
cv = ev - ac
spi = ev / pv
cpi = ev / ac
print(f"BAC: {bac:,}") # BAC: 100,000
print(f"EV: {ev:,.0f}") # EV: 40,000
print(f"SV: {sv:,.0f}") # SV: -10,000
print(f"CV: {cv:,.0f}") # CV: -5,000
print(f"SPI: {spi:.2f}") # SPI: 0.80
print(f"CPI: {cpi:.2f}") # CPI: 0.89Reading variances and indices
Schedule variance (SV) and cost variance (CV) are differences in money. Schedule performance index (SPI) and cost performance index (CPI) are ratios that show efficiency.
- A negative SV or CV means the project is behind schedule or over budget.
- An SPI or CPI below 1.0 means the project delivers less value than planned or spent.
Exercise
In the example, the Build package is reported at 60 percent instead of 40 percent. What are EV, SV, and CV, with PV 50,000 and AC 45,000?
Show answer
EV is 20,000 + 0.6 × 50,000 + 0 = 50,000. SV is 50,000 − 50,000 = 0, and CV is 50,000 − 45,000 = 5,000. The project looks on schedule and under budget, but only because the progress figure is inflated.