Sub topic 3
Reading the S-curve of PV, EV, and AC
This chapter assumes you know how a work breakdown structure (WBS) divides scope into work packages, and that you can calculate planned value (PV), earned value (EV), and actual cost (AC) at a status date.
Reading the S-curve of PV, EV, and AC
Plot cumulative PV, EV, and AC against time. Each curve usually forms an S shape: work starts slowly, peaks during execution, and tapers at the end. PV shows the plan. If EV trails PV, the project is behind schedule. If AC rises above EV, the project is overspending.
Interpreting status: the four common cases
Schedule performance index (SPI) equals EV divided by PV. Cost performance index (CPI) equals EV divided by AC. A value of 1 means on plan.
Forecasting the estimate at completion
Estimate at completion (EAC) is the expected total cost. The common formula assumes the current CPI continues: EAC = BAC / CPI, where BAC is budget at completion.
bac = 100000
pv = 40000
ev = 30000
ac = 45000
spi = ev / pv
cpi = ev / ac
eac = bac / cpi
etc = eac - ac
vac = bac - eac
tcpi = (bac - ev) / (bac - ac)
print(f"SPI={spi:.2f} CPI={cpi:.2f}")
print(f"EAC={eac:,.0f} ETC={etc:,.0f} VAC={vac:,.0f} TCPI={tcpi:.2f}")Output: SPI=0.75 CPI=0.67 and EAC=150,000 ETC=105,000 VAC=-50,000 TCPI=1.27.
Estimate to complete and variance at completion
Estimate to complete (ETC) is the remaining cost: ETC = EAC - AC. Variance at completion (VAC) is the expected final gap: VAC = BAC - EAC. A negative VAC signals an overrun.
TCPI: the efficiency still required
To-complete performance index (TCPI) is the cost efficiency needed for the remaining work to finish within budget: TCPI = (BAC - EV) / (BAC - AC). Here it is 1.27, while the current CPI is 0.67. Finishing on budget would require spending far more efficiently than the project has so far, so the budget target is probably unrealistic.
Why SV and SPI mislead late in a project, and earned schedule
Schedule variance (SV) and SPI measure schedule in money. Late in a project, PV approaches BAC, so SPI drifts toward 1 even when the project is late. Earned schedule (ES) measures progress in time units: it is the planned time at which the current EV was scheduled. Schedule performance then becomes ES divided by actual time elapsed.
Data quality and common pitfalls
- Optimistic percent-complete reporting inflates EV and hides schedule problems.
- Incomplete actual-cost capture understates AC, which makes CPI look better than it is.
- Use one currency and one cutoff date for PV, EV, and AC.
Exercise
With BAC 100,000, EV 30,000, and AC 45,000, what is TCPI, and is finishing on budget realistic?
Show answer
TCPI = (100,000 - 30,000) / (100,000 - 45,000) = 70,000 / 55,000 ≈ 1.27. The project must spend about 1.27 of budget per unit of work done, while it has been achieving 0.67 (CPI). Finishing on budget is unlikely without a major change.