Sub topic 14
Using the SIPOC in a Project Charter and Detailed Process Map
This chapter assumes you can already build a SIPOC diagram: you know the five columns, you can set process boundaries, and you can write four to seven high-level steps. It covers what to do with the finished diagram. A SIPOC that sits in a folder after the Define workshop has wasted most of its value. This chapter shows how its content feeds a project charter, a detailed process map and a voice-of-the-customer study, and which errors appear when teams carry it forward.
Why the handoff matters
A SIPOC is a scoping tool. It answers "what is in this process, who touches it, and what does it produce?" Later DMAIC work (Define, Measure, Analyze, Improve, Control) needs those answers repeatedly. If each later document restates the scope in its own words, the documents drift apart. The usual result is a charter that promises one thing, a process map that covers another, and a data collection plan that measures a third.
Treat the SIPOC as the reference for scope. Every later artifact should be traceable back to a specific cell in it.
| SIPOC element | Feeds into | What it supplies |
|---|---|---|
| Process start and end points | Project charter | The scope statement and the in-scope and out-of-scope lists |
| Process steps | Detailed process map | The top-level boxes that get broken down |
| Outputs and customer requirements | Voice-of-the-customer study, charter goal | Candidate critical-to-quality measures |
| Customers | Stakeholder list, interview plan | Who to ask about requirements |
| Inputs and suppliers | Data collection plan, risk list | Where variation can enter, and who to talk to about it |
Carrying the SIPOC into the project charter
A project charter is a short document that authorizes a project. It usually holds a problem statement, a goal, a scope, a team, and a timeline. The SIPOC contributes most directly to the scope, and it also sharpens the problem and goal statements.
Scope from the boundaries
The first and last process steps give you the scope statement. For the order-fulfilment example used in this tutorial, the boundaries are "Receive order" (start) and "Invoice customer" (end). The charter scope can then be written almost word for word:
- In scope: all activities from receipt of a confirmed customer order to issue of the invoice.
- Out of scope: order generation by the sales team, carrier operations after handover, payment collection.
The out-of-scope list matters as much as the in-scope list. It is where you record the things stakeholders will ask about halfway through the project. Anything the SIPOC leaves outside the boundary should be named here, so that a request to "also fix payment chasing" is visibly a scope change and not a small addition.
Problem and goal from outputs and requirements
Outputs and their customer requirements give you something measurable to put in the problem statement. A vague problem statement such as "fulfilment is slow" becomes specific when you tie it to an output and a requirement:
- Output: Packed parcel.
- Customer: Customer.
- Requirement: Delivered within three working days of order.
- Problem statement: "In the last quarter, 22% of orders were delivered later than three working days after order confirmation."
The percentage here is an illustration of the form, not a real figure. The structure is what to copy: output, customer, requirement, measured gap.
Stakeholders and team
The Customers and Suppliers columns are a ready-made stakeholder list. Each named group is either affected by the project or can affect it. Use the list to decide who is on the core team, who is consulted, and who is only informed. In the example, the Shipping team and Finance team both appear in the diagram, so both should be considered for the team or at least for interviews.
## Project charter (extract)
**Process:** Order fulfilment
**Start:** Customer order is confirmed (Receive order)
**End:** Invoice is issued (Invoice customer)
**In scope:** Receive order, Check stock, Pick and pack, Ship order, Invoice customer
**Out of scope:** Order generation, carrier operations after handover, payment collection
**Problem statement:** Orders are delivered late against the three-working-day requirement.
**Primary output:** Packed parcel
**Primary customer:** Customer
**Stakeholders (from SIPOC):**
- Suppliers: Sales team, Warehouse system owner, Carrier, Finance team
- Customers: Customer, Shipping team, Finance teamCarrying the SIPOC into the detailed process map
The SIPOC shows five to seven steps. A detailed process map shows the actual work: decisions, handoffs, waiting, rework loops and who does each task. The SIPOC tells you where to begin and how far to go.
Expand each step, one at a time
Take each high-level step and ask: "What happens, in order, between the input arriving and the output leaving this step?" Each SIPOC step becomes a section of the detailed map. For "Check stock," the expansion might include looking up stock levels, deciding whether stock is sufficient, and either releasing the order to picking or raising a backorder.
Keep the numbering linked. If the SIPOC step is 2, the detailed steps are 2.1, 2.2, 2.3. That makes it easy to see which high-level step a detail belongs to, and to find where a problem sits.
Use the boundaries as hard edges
The detailed map starts and ends where the SIPOC does. Teams often discover extra activity while mapping, such as a manual reconciliation done before the order is received. If it falls outside the boundary, note it and leave it off the map. If it seems essential, go back to the charter and agree a scope change.
Use inputs and outputs to check handoffs
Each step's output should be the next step's input. Compare the detailed map against the SIPOC for these checks:
- Every output in the SIPOC appears as an output of some detailed step.
- Every input in the SIPOC is used by some detailed step.
- Every detailed handoff between people or systems is either inside the process or crosses the boundary to a named supplier or customer.
A mismatch is a finding. An input that no detailed step uses may mean the SIPOC is wrong, or that the process has a wasted activity such as collecting data nobody reads.
Carrying the SIPOC into a voice-of-the-customer study
Voice of the customer (VOC) is the practice of collecting what customers actually need, usually through interviews, surveys, complaints and usage data. The SIPOC gives you the starting list.
- The Customers column tells you who to include. Do not skip internal customers such as the Shipping team. Their needs affect the external customer's experience.
- The Outputs column tells you what to ask about. Ask each customer group about each output they receive, not about the process in general.
- The requirements you wrote in the workshop are hypotheses. The VOC study tests them. Customers sometimes want something different from what the team assumed, such as a delivery window instead of a delivery speed.
The result of VOC work is a set of critical-to-quality (CTQ) requirements, which are specific and measurable. Update the SIPOC's requirement notes with the confirmed CTQs and re-issue it. Then the charter goal, the data collection plan and the SIPOC all use the same numbers.
Keeping the SIPOC alive
Treat the SIPOC as a versioned document. When the charter scope changes, change the SIPOC first and then update the dependent documents. Add a version number and date to the page. A short change log, with one line per change and the reason, is enough.
Revisit the SIPOC at phase gates. At the end of Measure you will have real data, and the data sometimes shows that a step is missing, or that an input has a supplier nobody listed. Correct the SIPOC so that Analyze and Improve work from the right picture.
Common errors when using the SIPOC downstream
- Copying the SIPOC into the charter without the boundaries. The charter then says "improve order fulfilment" with no start and end. Always copy the start and end explicitly.
- Letting the detailed map grow past the boundary. Extra activity gets mapped, the project balloons, and the charter no longer matches the work.
- Treating requirements as facts. Workshop-stage requirements are guesses until VOC confirms them. Label them as draft.
- Never updating the SIPOC. After a scope change the SIPOC still shows the old process, and new team members read the wrong picture.
- Skipping the traceability checks. Without the input and output comparison, gaps between the high-level and detailed views go unnoticed until the Analyze phase.
Exercise
Exercise
A team's SIPOC for "Handle customer complaint" starts at "Receive complaint" and ends at "Close case". While building the detailed map, they find that many complaints are caused by errors in how the sales team records orders. A team member proposes adding "Review order entry" as a step on the map. What should the team do, and which documents change if they accept the proposal?
Show answer
The proposed step is outside the SIPOC boundary, so it should not be added to the detailed map on the team's own initiative. The team should record it as an out-of-scope finding and take it to the sponsor as a scope question. If the sponsor accepts it, the order is: update the SIPOC first (new start point or a new step, and the sales team moves from supplier to a process participant), then the charter scope and in-scope/out-of-scope lists, then the detailed map. If the sponsor declines, the finding goes in the charter's out-of-scope list or a handover note for a separate project.
Exercise
Using the order-fulfilment SIPOC from this tutorial, write one charter problem statement in the form output, customer, requirement, measured gap. Then name which customers you would include in the voice-of-the-customer study.
Show answer
Example: "The Packed parcel output for the Customer must arrive within three working days of order confirmation. Last quarter, X% of orders missed this requirement" (X comes from real data). The VOC study should include the external Customer for the parcel and confirmation, the Shipping team for picked items and packed parcels, and the Finance team for the invoice and shipping notice. Internal customers are included because their needs affect the external customer's result.