Writing Acceptance Criteria
This chapter assumes you know how a project is organized, what a deliverable is, and how stakeholders review and approve work. You should also understand the basic idea of a scope statement.
Writing acceptance criteria
Acceptance criteria are the conditions a deliverable must meet before the sponsor or customer accepts it. Each criterion should be testable, so someone can check it and answer yes or no.
Vague wording cannot be tested. "The portal should be easy to use" gives no way to decide whether the work is done. A testable version reads: "A user can reset a password using a link sent to their registered email."
Write each criterion with three parts: the actor, the action, and the observable result. Add a limit, such as a time or a count, when one matters.
deliverables:
- id: D1
name: Self-service password reset
acceptance_criteria:
- A user can reset a password using a link sent to their registered email
- The reset link expires after 24 hoursStating exclusions explicitly
Exclusions list work that is out of scope. Without them, stakeholders often assume that a related feature is included. An exclusion closes that gap in writing.
exclusions:
- Mobile application changes
- Migration of historical support tickets
- Single sign-on integrationRecording assumptions and constraints
An assumption is a condition you believe is true but have not verified. A constraint is a limit the project must work within. Record both, because a wrong assumption or an ignored constraint can break the schedule.
assumptions:
- The existing identity service remains available during the project
constraints:
- Launch must occur before the end of the fiscal yearExercise
Exercise
Rewrite "The page loads fast" as a testable acceptance criterion.
Show answer
Example: "The account settings page finishes loading within 2 seconds for 95% of page views, measured over one week." Accept any answer that names a metric, a threshold, and a way to measure it.