Sub topic 1
What Project Scope Is and Why Its Boundary Matters
Prerequisites
This chapter assumes you understand how projects are organized and run, can name common roles such as sponsor, project manager, and team member, and have worked with a stakeholder or customer on a deliverable.
Project scope and product scope
Two kinds of scope
Product scope is the set of features and characteristics of the result. Project scope is the work the team must do to deliver that result. A project can build the right product and still fail if its work keeps expanding, so both must be stated.
The boundary matters because it defines what the team commits to. Without a boundary, each new request looks reasonable, and the schedule and budget absorb work nobody planned.
Starting from objectives and success criteria
Begin with the business objective, then convert it into a measurable success criterion. For example, "reduce support tickets about account access by 20% within 6 months of launch" gives the team a number to check. An objective without a measure cannot show when scope is complete.
Gathering stakeholder requirements
List every group affected by the project, then record what each group needs. Requirements describe needs. Solutions come later. Record the source and owner of each requirement so that later disputes have a clear trail.
Defining deliverables
A deliverable is a verifiable output the project produces, such as a self-service password reset feature. Name each deliverable, link it to the requirements it satisfies, and keep the list short enough to review in one meeting.
deliverables:
- id: D1
name: Self-service password reset
requirements: [R-04, R-05]Exercise
A stakeholder says "make the portal faster." Why is this not yet a usable requirement, and what should the team ask for?
Show answer
It has no measure or owner. The team should ask which page or action must be faster, by how much, and by when, so the requirement can be tested.