Sub topic 3
Assembling the Scope Statement
Prerequisites: This chapter assumes you know how projects are organized, can name the sponsor, project manager, and team members, and have worked with a stakeholder on a deliverable.
Assembling the scope statement
A scope statement is one document that combines the deliverables, their acceptance criteria, the exclusions, the assumptions, and the constraints. Each part answers a different question: what we will deliver, how we will know it works, what we will not do, and what we are relying on.
project: Customer Portal Refresh
objective: Reduce account access tickets by 20% within 6 months of launch
deliverables:
- id: D1
name: Self-service password reset
acceptance_criteria:
- The reset link expires after 24 hours
exclusions:
- Single sign-on integration
assumptions:
- The identity service remains available
constraints:
- Launch before fiscal year endDecomposing deliverables into a work breakdown structure
A work breakdown structure (WBS) is a tree that splits each deliverable into smaller work packages. Every package traces back to a deliverable ID, so any work without a parent is visibly out of scope.
1 Customer Portal Refresh
1.1 Self-service password reset (D1)
1.1.1 Design reset flow
1.1.2 Test reset flowManaging scope creep with change control
Scope creep is extra work added without a formal decision. A change request (CR) records the new ask, notes whether it is currently excluded, and holds the decision until its effect on schedule, cost, and risk is estimated. The change authority then approves, rejects, or defers it.
Validating scope and obtaining sign-off
Scope validation checks each completed deliverable against its acceptance criteria. The sponsor or customer then signs off on each one. Accepted deliverables stay fixed, and any later change goes through change control.
Exercise
A stakeholder asks for single sign-on during build. Which part of the scope statement shows it is not yet agreed work, and what should happen next?
Show answer
The exclusions list shows single sign-on as out of scope. The request should be logged as a change request and assessed for schedule, cost, and risk before the change authority decides.