Sub topic 5
Writing acceptance criteria
Acceptance criteria are the conditions a deliverable must meet before the customer accepts it. This chapter assumes you can already name the deliverables of a project and know who the sponsor and other stakeholders are. It shows how to write criteria that two people can check independently and reach the same verdict.
What acceptance criteria do
A deliverable name such as "Self-service password reset" tells the team what to build but not when it is finished. Acceptance criteria supply the finish line. They convert a deliverable from a noun into a testable claim.
Criteria do three jobs:
- They tell the team when to stop. Without them, work continues until someone runs out of patience, or it stops too early.
- They give the stakeholder a fair test. The customer can check the result against what was agreed instead of against a changed opinion.
- They feed scope validation. At sign-off, the criteria are the checklist the sponsor uses to accept or reject the deliverable.
Acceptance criteria are not the same as a requirement, a task, or a definition of quality in general.
- A requirement states a need ("users must be able to recover access to their account").
- A task is a unit of work ("build the reset email").
- An acceptance criterion states an observable outcome that proves the need is met ("the reset link expires after 24 hours").
Each deliverable usually has several criteria. Together they define what "done" means for that deliverable, and nothing beyond them is promised.
Properties of a good criterion
A criterion is useful only if a reviewer can look at the finished deliverable and answer "met" or "not met" without asking the author what they meant. Check each criterion against these properties.
| Property | Question to ask | Failing example |
|---|---|---|
| Observable | Can someone see or measure the outcome? | "The page feels intuitive" |
| Unambiguous | Would two reviewers read it the same way? | "Reset works quickly" |
| Specific to one outcome | Does it test one thing? | "Users can reset, change, and delete their password" |
| Independent of design | Does it state the result, not the implementation? | "Use a SHA-256 token table" (unless the design is a real constraint) |
| Agreed | Did the acceptor and the builder both approve it? | Criteria written only by the delivery team |
| Traceable | Does it map to one deliverable? | A criterion that applies to "the project in general" |
The first two properties cause most failures. Words such as "fast", "user-friendly", "secure", "robust", and "as needed" are placeholders for a number or a test that nobody has written yet. Replace each one with a measurement, a threshold, or a named check.
Rewriting weak criteria
The table shows common weak criteria and how to sharpen them. The numbers in the "stronger" column are examples. Use values your stakeholders actually agree to.
| Weak criterion | Problem | Stronger criterion |
|---|---|---|
| The reset process is easy to use | Subjective | A first-time tester completes a reset in under 3 minutes without help, in 4 of 5 trials |
| The reset email arrives quickly | No threshold | The email is sent within 60 seconds of the request, measured in the test environment |
| The link is secure | Undefined | The link works once and stops working after use or after 24 hours, whichever comes first |
| Settings are saved | No context | After saving, reloading the settings page shows the new values |
| Works on all browsers | Unbounded | Passes the test script in the two latest versions of Chrome, Firefox, Safari, and Edge |
"All browsers" is a scope problem as much as a wording problem. It leaves the boundary open. A criterion that names the supported set also acts as a small exclusion: unlisted browsers are out of scope.
Choosing a format
There is no single correct format. Pick one that your acceptors can read and your team can test, and use it consistently.
Checklist
A checklist is a list of plain statements, each true or false. It works for most business deliverables and is the format used in the scope statement from this tutorial.
deliverables:
- id: D1
name: Self-service password reset
acceptance_criteria:
- A user can reset a password using a link sent to their registered email
- The reset link expires after 24 hours
- A used reset link cannot be used a second time
- The email is sent within 60 seconds of the requestThe first two criteria come from the scope statement example. The last two are refinements: they make the behavior of the link and the timing testable.
Given, When, Then
Scenario format describes a starting state (Given), an action (When), and an expected result (Then). It is useful when behavior depends on conditions, because each scenario fixes one condition.
Scenario: Expired reset link is rejected
Given a reset link was issued 25 hours ago
When the user opens the link
Then the page shows a message that the link has expired
And the password is not changed
Scenario: Reset for an unregistered address
Given no account exists for "[email protected]"
When someone requests a reset for that address
Then the page shows the same confirmation message as for a registered address
And no email is sentThe second scenario is a negative case: it states what must not happen. Negative cases are easy to forget and are often where disputes arise later.
Rule-based
A rule-based list states constraints that always hold, such as "passwords must be at least 12 characters". It suits validation rules, calculations, and policies. A rule can be combined with scenarios that illustrate it.
| Format | Best for | Weakness |
|---|---|---|
| Checklist | Most deliverables, documents, configurations | Conditions and edge cases are easy to hide in one line |
| Given, When, Then | Behavior that depends on state or sequence | Verbose for simple deliverables |
| Rule-based | Validation, calculations, policies | Does not show how the rule appears to the user |
What to cover
A deliverable with only "happy path" criteria will pass acceptance and still disappoint. Walk through these categories for each deliverable and keep the ones that matter.
- Functional behavior. What the deliverable does when used as intended.
- Edge and error cases. Expired links, empty fields, duplicate requests, unknown users.
- Non-functional qualities. Response time, availability, accessibility, security, supported platforms. State each with a number or a named standard.
- Data and content. Which records, languages, or document sections must be included.
- Documentation and handover. User guide, training session, runbook, if they are part of the deliverable.
Not every category applies to every deliverable. A written report might need only content and format criteria. A software feature usually needs all five. The point is to decide deliberately, not to inherit whatever the author first thought of.
Keep criteria within the deliverable
Each criterion should test something the deliverable itself controls. "Support tickets about account access fall by 20%" is an objective measure of project success, not an acceptance criterion for D1. It depends on user behavior and time after launch, and no one can verify it at handover. Keep it with the objective, and keep acceptance criteria for conditions that can be checked when the deliverable is delivered.
A worked example
Take D2, "Updated account settings page", from the Customer Portal Refresh. The original criteria are:
- Users can change name, email, and notification preferences
- Changes are saved and shown on the next page load
A reviewer could reasonably ask several questions. What happens if the new email is already in use? Does changing the email require confirmation? Are notification preferences a fixed list? Each unanswered question is a potential dispute at sign-off. Resolving them gives:
- id: D2
name: Updated account settings page
acceptance_criteria:
- A signed-in user can change name, email, and notification preferences on one page
- After saving, reloading the page shows the saved values
- Notification preferences offer the three options listed in the requirements document (v1.2)
- Entering an email already used by another account shows an error and saves nothing
- A changed email takes effect only after the user confirms it from a link sent to the new address
- The page passes the accessibility checks in the agreed test plan at level AA
verification:
method: Test script TS-D2 run in the staging environment, witnessed by the product ownerThree things changed. The vague "notification preferences" now points to a versioned document, so the boundary does not drift. Two edge cases are explicit. The final criterion is checked by a named method, and the verification block records who verifies it and where. That block is optional, but it removes a common argument about what counts as evidence.
Notice that single sign-on is nowhere in these criteria. It is listed under exclusions in the scope statement. If someone argues the settings page "should" support it, the criteria and the exclusions together answer the question, and any real need goes through change control.
Agreeing the criteria
Criteria are only useful if the person who will accept the deliverable has agreed to them before work starts.
- The project manager or business analyst drafts them, often with the delivery team, because the team knows what is testable.
- The acceptor (sponsor, customer representative, or product owner) reviews and approves them.
- The approved version is stored with the scope statement and changed only through change control.
Reviewing criteria with the delivery team also catches infeasible items early. A criterion that no one can test is better discovered during planning than at handover.
Common errors
- Criteria written after the work. They then describe what was built rather than what was needed, and the acceptor has no real test.
- Hidden design decisions. "The system stores tokens in a database table" prescribes a solution. Write the outcome, and state a design choice only when it is a genuine constraint.
- Compound criteria. "Users can reset and change passwords" can half-pass. Split it so each line has one verdict.
- Unmeasured quality words. "Fast", "intuitive", and "reliable" invite disagreement. Attach a number, a method, or a standard.
- Missing negative cases. Specify what must not happen, such as an expired link changing a password.
- Too many criteria. Fifty trivial items hide the five that matter. Group by importance and drop duplicates.
- Silent updates. Editing criteria mid-project without a change record is scope change in disguise.
How criteria connect to the rest of the scope
Acceptance criteria sit between the deliverable and the scope statement. The scope statement lists each deliverable with its criteria and its exclusions. The work breakdown structure then breaks the deliverable into work packages, and the test packages, such as "Test reset flow", exist to produce evidence against the criteria. At the end of the project, scope validation takes the same criteria and uses them as the basis for formal acceptance. If the criteria are weak, every later step inherits the weakness.
Exercise
A deliverable "Monthly sales dashboard" has the criterion "The dashboard loads fast and shows accurate numbers." Rewrite it as at least three criteria that a reviewer could mark as met or not met. State one thing that would remain outside the criteria and should be written as an exclusion.
Show answer
One acceptable answer: (1) The dashboard's main view loads within 3 seconds for a data set of 12 months of sales, measured in the test environment. (2) Total monthly revenue on the dashboard matches the finance system's monthly report to the cent for each of the last 6 months. (3) The dashboard shows revenue by region and by product category, using the region and category lists in the requirements document. A fair exclusion: forecasting or predicted sales figures are not included. The rewrite works because "fast" gets a threshold and a method, "accurate" is tied to a named source and a comparison, and the compound statement is split so each line has a single verdict. Any exclusion that states a plausible expectation not covered by the criteria is acceptable, such as mobile layout or export to spreadsheet.
Exercise
Reviewers disagree whether "The reset link is secure" is met. Name two problems with this criterion and propose a replacement that fixes them.
Show answer
The criterion is subjective, because "secure" has no defined test, and it is not specific to one outcome, because security covers many behaviors such as expiry, reuse, and interception. Replace it with testable statements such as "The reset link stops working after it is used once" and "The reset link stops working 24 hours after it was issued". Each statement can be tested with a clear pass or fail. If a security standard applies, add a criterion naming it and the test that demonstrates conformance.